|
March 9, 2001 P.S. Protest No. 00-24 XTRA LEASE, INC. Solicitation No. NTL 00-001
Decision XTRA Lease, Inc. (XTRA), protests the revision of the delivery schedule of a contract for the lease of truck trailers in connection with its delayed award, contending that the competition should have been reopened instead. On April 28, 2000, National Mail Transportation Purchasing at Postal Service headquarters issued solicitation NTL 00-001 seeking (as revised by four amendments) 4,406 trailers for lease over a six-year contract term. The trailers of various sizes were to be delivered to numerous postal facilities nationwide on two delivery dates: 1,637 were to be delivered on "delivery date A," September 10, 2000, and 2,769 were to be delivered on "delivery date B," July 1, 2001. Amendment Modification 1, May 15, revised the solicitation provision setting out these dates by adding the following: "These contract/delivery dates in the initial term and any renewal term may be adjusted at the discretion of the Contracting Officer." The solicitation contemplated a two stage process: In the first stage, offerors were to submit written technical/management proposals which the Postal Service would evaluate to prequalify offerors to participate in the second stage. The second stage was an on-line reverse auction called a competitive bidding event (CBE) in which offerors would submit prices expressed in terms of a daily rental rate per trailer. While the initial solicitation provided for award only in the aggregate for the entire quantity of trailers, it was amended to provide for award either in the aggregate or on the basis of seven individual DN groups. Proposals were due on May 26; the CBE was to be held on June 8. Solicitation provision K.2, Modification or Withdrawal of Proposals and Acceptance Period, provided that technical proposals could be withdrawn prior to the start of the CBE, but that "after the CBE has begun and the offeror has submitted a price bid, it may not withdraw its proposal prior to expiration of the proposal acceptance period." The acceptance period was established as "60 days after the date of the CBE or a longer period proposed by an offeror." A preproposal conference was held on May 8. It included the following: [Q.] When do you anticipate the award? [Contracting Officer] Contract award should take place within seven days after the competitive bidding event has completed [sic]. Give us a week to do our best value determinations, clean up any loose ends. It should occur about a week after. Sometime before the middle of June the contract should be awarded.[1] * * * [Q.] In the event that theres appeals and delays on the Postal Service and, you know, it stretches out to 50 days before theres an award made, is the time frame for getting the trailers in going to be extended? . . . . [Contracting Officer] . . . . Let me say that we feel as though theres enough time in the schedule to be able to address any unusual occurrences that may come about to ensure ample time in the delivery schedule to allow for the proper delivery. Were sure theres ample time in the schedule to allow you for [sic] enough time to deliver the trailers as required to the various locations, assuming youre awarded a contract. XTRA submitted its proposal in the first phase of the competition. It took exception to two aspects of the requirement. First, XTRA proposed a revised delivery schedule, offering to provide delivery of 259 trailers to three DN groups on September 10, and the balance due for delivery date A on November 10, and to postpone delivery of all of the quantity due on delivery date B from July 1, 2001, to August 1, 2001. Second, XTRA took exception to the requirement at B.4 of the solicitation that "the supplier will be a preferred supplier with respect to the DN groups to which the suppliers contract is applicable[,] . . . required to provide . . . additional trailers needed within the applicable DN group at the prevailing per trailer, per day rate . . . ." The contracting officer states that he sought clarification of these two exceptions from XTRA, and that in a discussion on June 5 he advised XTRA that "these [exceptions] would most likely result in a low technical score, and might preclude XTRA from becoming a prequalified supplier." He also states that he advised "that if XTRA opted to withdraw from the procurement, they must do so in writing." XTRAs version of that discussion differs in asserting that it initiated the conversation, that it requested a revision of delivery date A, and that in the absence of the revision (which the contracting officer declined to make) it announced it would have to withdraw its offer. By letter dated June 6, XTRA requested that it be "remove[d] . . . from the bidding process." The CBE was held, as scheduled on June 8. XTRA did not participate. The lowest overall daily rate for the total quantity of trailers was proposed by Transport International Pool (TIP). Award did not occur in mid-June. The contracting officer states that TIP was advised that the Postal Service had accepted its proposal on September 72. Under the awarded contract, delivery of the initial quantity (those due on delivery date A) was to be completed by November 30. The other offerors who had participated in the CBE were advised of the award by letters dated September 7. XTRA states that it learned of the contract award from the Postal Service on September 8, and that it learned of the extension of delivery date A to November 30 on September 21 from a Denver, CO, postal representative in the course of a telephone conversation inquiring whether XTRA could provide holiday trailers. XTRAs protest was received on September 25. It contends that the award to TIP was improper because TIPs proposal failed to meet the solicitations required delivery dates, because the Postal Service arbitrarily failed to amend the solicitations delivery schedule as XTRA had requested while intending to relax it subsequently to TIPs advantage, or because the Postal Service failed to amend the delivery schedule when award was delayed. XTRA explains that the quantity of trailers containing the "unique" features which the Postal Service sought were "not readily available on the commercial market," and that because of market conditions, XTRA could not, in good faith, propose on the total requirement for delivery on delivery date A or agree to the preferred provider provision of the solicitation. Accordingly, it qualified its offer in that respect. It then asserts, as recited above, that it withdrew its offer when the contracting officer declined to extend the first delivery date. XTRA asserts that had the delivery schedule been extended, as it claims it later was for TIP, "prior to the CBE, as it should have been, XTRA would not have been forced to withdraw from the CBE, would have submitted a fully conforming and unqualified technical proposal, and likely would have been able to underbid TIP and receive award . . . ." XTRA contends that its protest is timely under both the requirements of Purchasing Manual (PM) 3.6.4.c., that it "be received within 15 days after award of the contract," here assumed to be September 8, and extended to the first business day after the 15th day, September 23, a Saturday, per PM 3.6.2.d; and "not later than 10 days after the basis of protest is known or should have been known," here September 21, when XTRA first learned "that Delivery Date A had been relaxed for all DN Groups." It also contends that it has standing, as "an actual or prospective offeror whose direct economic interest would be affected" (PM 3.6.2.a.), despite its withdrawal from the competition because it had participated in the procurement before the withdrawal, citing cases from various non-postal fora "that a protester that . . . withdraws its proposal as a result of violations of the law and without knowledge thereof, can later protest once it acquires that knowledge." On the merits, XTRA contends that the Postal Service failed to comply with PM 4.2.2.i(1)s requirement that solicitations be amended when changes in delivery schedules are required and improperly accepted TIPs nonconforming technical proposal, which XTRA assumes "indicated a November 30 delivery date";3 and "improperly denied XTRAs request to amend the solicitation with the intention of later relaxing the specification for TIP" (initial capitals omitted).4 The contracting officers statement includes the following jurisdictional objections:
On the merits, the contracting officers statement makes the following contentions, among others:
XTRA responded to the contracting officers statement in submissions which made the following points:
[I]f the agency knows that a potential offeror was excluded from the competitive range for a reason that no longer exists after a subsequent amendment relaxing the solicitations terms, the offeror should be notified of the changes, especially of any relaxed requirements, since the firm, after the amendment, is potentially fully capable of fulfilling the agencys needs. We think this principle equally applies where an offeror withdraws from the competition because of a restrictive delivery schedule which is subsequently relaxed, where the agency is aware that the firms reason for leaving the competition was directly related to the strict delivery requirements which are later . . . . [XTRAs emphasis.]
The awardee, TIP, submitted comments on the contracting officers statement and on XTRAs response in two rounds of submissions:
The contracting officer responding to XTRAs comments asserting the accuracy "to the best of [his] recollection" of his previous submissions. The contracting officer notes his factual disagreement with XTRA about whether XTRA requested an amendment of the solicitation, refers to the discussion of delivery dates in the pre-proposal conference, quoted supra, as evidence that he "was not [then] anticipating a delay in the delivery schedule as the result of internal policy debates or to favor a particular supplier," but explains that "[i]n early July [he] was asked to study the merits of buying vs. leasing trailers," a study which was not completed until mid-August, delaying the award to September. Accompanying this submission were various documents relating to the lease/purchase analysis (but not any documents indicating when the analysis was ordered), and correspondence in July through September relating to the award. XTRA commented on the contracting officers submission and TIPs comments:
Discussion Because they are jurisdictional, we turn first to the issues involving the protesters standing and the protests timeliness. With regard to standing, the issue is whether XTRA is an interested party "whose direct economic interest [was] affect by the award of [the] contract." PM 3.6.2.a. The relief which XTRA seeks is the recompetition of the requirement with a relaxed initial delivery schedule consistent with that which TIP was given. It is clear from XTRAs technical proposal and its discussion of the delivery schedule with the contracting officer prior to its decision to withdraw its offer that it viewed the original initial delivery schedule as a barrier to its competition, so that a recompetition on a relaxed schedule would affect its direct economic interest.15 This case is thus dissimilar from Federal Data, where the protester lacked that interest because its protest did not seek the chance to compete again, and akin to Information Ventures, as the protester contends. Accordingly, XTRA has standing to protest.16 As all the parties recognize, the timeliness of XTRAs protest is measured by the requirement at PM 3.6.4.d that the protest "be received not later than 10 days after the basis of the protest is known or should have been known." (Emphasis added.)17 Here, XTRA knew of the award on September 8, and it then knew (or should have known) that information about the delivery schedule of TIPs contract was relevant to its (potential) claim.18 However, XTRA took no affirmative steps to inquire concerning that important fact. Instead, it learned of TIPs actual delivery schedule only when so advised by a postal representative in an unrelated context. The General Accounting Offices protest decisions discuss a protesters obligation diligently to pursue its protest in various circumstances, including seeking information which would have been evident from review of publicly opened bids or provided in debriefings or in response to formal information requests. (See, e.g., Thomas May Construction Company, Comp. Gen. Dec. B-255683, March 23, 1994,, 94-1 CPD ¶ 210 (protester did not diligently pursue basis of protest based on information publicly available at the bid opening when it sought the information under FOIA only after award) and Ranco Construction, Inc., Comp. Gen. Dec. B-281242, January 12, 1999, 99-1 CPD ¶ 11 (protest of bids nonresponsiveness raised after award untimely, citing Thomas May); Geo-Centers, Inc., Comp. Gen. Dec. B-276033, May 5, 1997, 97-1 CPD ¶ 182 (protest timely when "protester clearly sought a debriefing within 10 days of learning of the award, and diligently sought more information at each step in the processat no point allowing more than 10 days to pass before making its next request"); J&J Maintenance Inc., Comp. Gen. Dec. B-223355.2, August 24, 1987, 87-2 CPD ¶ 197 (protest untimely when "protester waited 3 weeks from notice of cancellation of the solicitation to orally request information . . . and then waited an additional 4 weeks before filing a Freedom of Information Act request," distinguishing cases in which FOIA requests were filed "within 1 to 25 days.") This case is not identical to any of the decisions which our research has disclosed, and the elapsed time between XTRAs notice of the award (September 8) and the filing of its protest (September 25) is shorter than any time period identified in those decisions as indicating an absence of diligence in pursuit of a protest. As in several of those decisions, however, XTRA took no identifiable steps to solicit the information which it required, and it was mere happenstance that it learned when it did of TIPs delivery schedule. Finding XTRAs protest timely in these circumstances would render the requirement that protests be filed within ten days of the date that they "should have been known" a nullity. Accordingly, XTRAs protest must be dismissed as untimely.19 We will, however, comment briefly on the omission which gave rise to the protest. The solicitation was deficient in failing to indicate an assumed date of award and a provision explaining the effect of delay in award beyond that date. As a recent decision has noted: We understand Purchasing Manual 2.2.5, Delivery or Performance Schedule, and Provision 2-2, Time of Delivery (January 1997), which it discusses, to contemplate the inclusion of an assumed date of award in all solicitations calling for delivery in terms of a calendar date . . . . Pitney Bowes Corporation, P.S. Protest No. 00-16, December 1, 2000.20 The amendment of the solicitation allowing the contracting officer to "adjust" the stated delivery dates did not remedy that defect in the solicitation, because the language did not give the Postal Service any right it did not already have under the Changes clause at H.8 of the solicitation,21 nor was there any indication that the adjustment was intended to relate to any change in the anticipated date of award. The protest is dismissed.
This advice was consistent with the milestone schedule in the Individual Purchase Plan for the purchase, which contemplated contract award on June 14. 2How the September 7 notification occurred is not clear from the record. In the course of the protest, the contracting officer furnished a copy of an e-mail message dated September 8 informing postal managers that the "contract has been awarded to TIP" that "[t]he effective award date of the contract is Saturday, September 9, and that the first quantity of trailers "will be in place by close-of-business November 30, 2000." The protest file contains a signed postal "Notice of Acceptance" dated September 9, and a copy of Form 7495, Transportation Services Bid or Proposal and Contract for Regular Service, signed on September 12 by both TIP and the Postal Service. These documents recite the annual rate of the contract as in excess of $16 million. 3This aspect of the protest may be summarily resolved since its premise is incorrect. TIPs technical/management proposal took no exception to delivery date A as established in the solicitation. 4The protests allegations include the following:
5Characterizing XTRAs contention as that the Postal Service suggested or required that it withdraw from the competition, the contracting officer demurs, asserting, rather, that he did no more than advise XTRA that the exceptions which it had taken to the delivery schedule and preferred provider provision "would most likely result in a low technical score and might preclude [its prequalification]." Further, responding to XTRAs assertion that it had to withdraw its offer because an award might require delivery of more trailers on September 10 than it could provide, the contracting officer contends that such a result would not have been possible under the terms of XTRAs offer. Federal Data involved review of a protest before the General Services Board of Contract Appeals under former 40 U.S.C. § 759, which allowed a protest by an "interested party" which was "an actual or prospective bidder or offeror" "whose direct economic interest would be affected by the award of the contract or by failure to award the contract." Federal Data had "knowingly taken itself out of the bidding" before filing the amended protest at issue in the suit, which did not seek to reverse the agencys purchase decision, but only sought bid preparation costs.7Alternatively, the contracting officer contends that XTRA should have protested the alleged restrictiveness of the solicitation before the May 26 date for the receipt of proposals, since it knew by that time that it could not meet the delivery requirement. XTRAs response to this contention correctly rebuts it. XTRA also contends, based on various extensions made to its Los Angles trailer contract, that the delivery dates for TIPs contract may have further extended to December 30, 2000, or March 31, 2001.9Citing Carl J. and Betty B. Kollenberg, P.S. Protest No. 97-05, June 4, 1997. 10Elsewhere in its comments, XTRA contends that its proposed revised delivery schedule should be understood as providing for 95 days of lead time (measured from the last possible award date, August 10, to November 10), which it views as "of the same order of magnitude as the 82 days afforded TIP. 11TIP rebuts XTRAs contention that the postal specification or delivery schedule were restrictive of competition by noting that nine offerors of the thirteen who proposed participated in the CBE. 12Citing L.A. Systems, Inc., Comp. Gen. Dec. B-276349, June 9, 1997, 97-1 CPD ¶ 206. 13Citing Dand Industries, Comp. Gen. Dec. B-233215, August 23, 1991, 92-1 CPD ¶ 193. 14TIP contends that XTRA cannot demonstrate the necessary "virtually irrefutable proof of malice and specific intent to harm the protester" (quoting Jenkins, Gales & Martinez, Inc., P.S. Protest No. 88-54, January 26, 1989). 15Cf. Cardion Electronics, 58 Comp. Gen. 591 (1979):
Cardions protest was denied on the merits, however, as the GAO concluded that the RFP as amended was not fundamentally different in purpose or nature from the original RFP. Further, in Cardion the GAO rejected the protesters after-the-fact suggestion that in deciding not to propose, it had detrimentally relied on provisions of the solicitation which were subsequently amended, noting that its "no-bid" message had set out unrelated circumstances as the grounds for its nonparticipation. XTRAs prior concern about the initial delivery schedule is a necessary condition to its standing. Whether it is a sufficient condition, in light of its further concerns about both delivery date B and the preferred provider provision, a solicitation requirement completely unrelated to any delivery timetable, need not be resolved for the reasons which follow. Cf. POVECO, Inc., Grumman Allied Industries, Inc., AM General Corporation, P.S. Protest No. 85-43, October 30, 1985:We reject the contracting officers suggestion that XTRA should of the basis for its protest as of September 10, delivery date A in the solicitation. Under XTRAs theory that the worst-case lead time was 34 days, delivery would not have been required until mid-October. The following decisions are consistent with this conclusion:
Policy Research Incorporated, Comp. Gen. Dec. B-200386, 1981 U.S. Comp. Gen. LEXIS 1798, March 5, 1981 (citations omitted, emphasis added).
Power Conversion Systems, Comp Gen. Dec. B-246654, February 26, 1992, 92-1 CPD ¶ 235 (emphasis added).
South Bend Lathe, Inc., Comp. Gen. Dec. B-216356, September 24, 1984, 84-2 CPD ¶ 343 (emphasis added). Alternatively, the solicitation, which was structured in many respects like a transportation services contract, might have included a description of the commencement of the contract term which related to the date of contract award. For example, in Lyndon Transport, Inc., P.S. Protest No. 91-85, February 7, 1992, the solicitation provided:
The similar provision in the solicitation involved in the more recent decision, Jody Whilden Blumenfeld, P.S. Protest No. 00-27, January 8, 2001, (not recited in the decisions text) provided:
Either formulation accomplishes the same purpose as Provision 2-2, which requires that when, as here, delivery dates are expressed in terms of specific calendar dates, an assumed date of contract award will be included in the solicitation and the Time of Delivery provision will provide that "[e]ach delivery date in the delivery schedule will be extended by the number of calendar days after the above [assumed delivery] date that the contract is in fact awarded." 21Among the allowed changes were "changes . . . in . . . [the d]elivery and performance schedule." |