|

February 24, 1995
P.S. Protest No. 94-48
WEM, INC.
Highway Contract Route Service, San Bernardino -- Los Angeles
Digest
Protest against exclusion of emergency contractor from solicitation of
bids from incumbents on existing highway contract routes to provide
additional service on their routes is denied where protester does not fit
the definition of incumbent and Procurement Manual regulation on limited
competitive procedures was followed.
Decision
WEM, Inc.,[1] protests its exclusion from
competition for the right to provide service on a mail transportation
contract operating between the San Bernardino Processing and Distribution
Center (PDC) and the Los Angeles Bulk Mail Center (BMC) (hereinafter
"the PDC - BMC route").
On June 7, 1994, the Pacific Area Distribution Networks Office (DNO)
terminated for default HCR 92314, a contract for the PDC - BMC route held
by John Moody. On June 17, the DNO awarded an emergency contract for
service to replace the defaulted contract to WEM. That contract provided
that it would end no later than December 2. WEM also held (and continues
to operate) a regular (non-emergency) contract on HCR 92355, San
Bernardino to La Quinta, CA.
The contracting officer considered alternative ways to obtain permanent
service to replace that provided by the defaulted contractor, including
issuing a regular transportation solicitation and the use of "limited
competitive procedures" to secure the service from incumbents
currently providing service on the PDC-BMC route.[2] The
contracting officer chose the second approach. On October 7, he sent
letters to Joe Garrett, Inc., and Yung Lee, the holders of regular PDC -
BMC contracts HCR 92318 and HCR 90093, respectively, giving each of them
the opportunity to submit sealed bids for additional service on their
routes. The letters stated that the opportunity to bid on additional
service was "[i]n accordance with U.S. Postal Service policy relative
to allocation of additional service to incumbent contractors who can
provide quality service." WEM was not invited to submit a bid.
Garrett submitted the lower bid for the additional service. The
contracting officer agreed to a modification of its contract to include
the solicited service effective December 1, but the required higher-level
postal approval of the modification had not been received before WEM's
protest of November 4 to the contracting officer. The protest complained
that only two bids had been sought, "disregarding other contractors
who may be interested, particularly [WEM], currently doing the run to the
satisfaction of all postal staff concerned." The contracting officer
orally advised WEM that no solicitation had been issued on which WEM could
bid. Before receiving a written disposition of its protest from the
contracting officer, WEM submitted a protest to this office, where it was
received on November 10.[3]
WEM protests the "noncompetitive" award of the route
previously operated by the defaulted contractor and then by itself as an
emergency contractor. The protest states that when WEM learned that the
Postal Service solicited bids from the two incumbents, it sought to submit
its own bid, but that the contracting officer refused it, citing the
"incumbency policy" as applying only to existing non-emergency
contracts serving the same termini.[4]
The protest argues that fulfilling the requirements through the
existing contracts rather than through full competition is improper in
this case because:
-- "The Route is . . . sufficiently large to support a great deal
of contractor interest and to be performed efficiently under a separate
contract."
-- The route "historically has been procured by the Postal Service
as a separate contract rather than a portion of another contract. . . .
Simply giving the Route to [another contractor on an existing route] at
the expiration of WEM's emergency contract violates USPS's obligation to
seek competition for such work."
-- Refusing to let WEM submit a bid and giving the route to another
incumbent contractor "without competition" violates PM 1.7.1
a., requiring "adequate competition whenever feasible," and
12.1.1, which applies the principle to transportation procurements.
-- The Mail Transportation Procurement Handbook (MTPH) requires that a
solicitation be issued when emergency contracts are to be replaced by
permanent highway contracts. MTPH 2.2.2.A.
-- "Noncompetitive awards are not permitted unless justified in
writing and approved in accordance with Management Instruction
AS-710-92-1, 'Noncompetitive Procurements'," citing PM 12.4.6 d.2.
"Upon information and belief, such approval was not obtained.
Assuming arguendo that such approval was obtained, it could not
have been rationally justified under the circumstances of this
case."
-- Limited competitive procedures "would apply only if USPS were
procuring 'additional service,' not re-procuring service [on] an
existing route," citing PM 12.4.6 d.3. Even under limited
competitive procedures WEM should have been permitted to submit a bid
because it was an incumbent under the PM's definition.
-- The route is also "beyond the scope of work contemplated under
Garrett's contract. Giving the Route to Garrett would thus constitute a
cardinal change to Garrett's contract," citing PM 12.4.12 c.2.
In his statement in response to the protest, the contracting officer
asserts that the incumbency policy did not apply to WEM in this case
because the incumbency policy "explicitly states that [it] does not
apply to emergency contracts. That is why the Protestor's emergency
contract was not considered as a basis for including the Protestor as a
bidder under the policy." See footnote 4. The contracting
officer asserts that contrary to the protester's contention, limited
competitive procedures were applicable in this case precisely because his
intent was to procure additional service on an existing route. He asks
that the protest be denied.
In reply to the contracting officer's statement, the protester
reiterates its argument that limited competitive procedures under PM
12.4.6 d.3 are inapplicable to the "re-procurement" of this
route, but that if they were, the rightful incumbent would be WEM. The
protester argues if the incumbency policy currently is viable,[5]
then emergency contractors may be considered incumbents under the policy:
The policy states that the policy itself does not apply to
"emergency contracts. . . ." Thus, "emergency
contracts" cannot be awarded on the basis of this policy. But the
policy does not exclude emergency contractors from being
considered incumbents for purposes of the policy.
[Emphasis in original.] The protester asserts that it is reversible
error for a contracting officer to fail to solicit an incumbent highway
contractor, citing Richard C. Gentry, Inc., P.S. Protest No. 94-33,
October 31, 1994, which applied to the solicitation of an emergency
contract. The protester concludes that "[i]f the procurement of an
emergency highway contract requires the incumbent contractor to be
included, then certainly the procurement of a less-urgent regular contract
requires the incumbent contractor to be included as well." Finally,
the protester states that it does not understand why the contracting
officer's decision could be in the best interests of the Postal Service
when WEM is operating the emergency contract at a lower rate than Garrett
would perform the additional service under its existing contract.
In rebuttal, the contracting officer asserts that the protester's
emergency contract did not qualify it for the incumbency policy because
"one cannot amend a[n] emergency contract to include a service change
that does not represent an emergency," citing 12.4.6 b.4.[6]
The contracting officer argues that since "no emergency existed"
as the protester's emergency contract expiration date neared, "it was
determined that it was not necessary to extend the emergency service.
Garrett and Lee were the only contractors who had existing non-emergency
contracts that met the requirements of 12.4.6 d.3 . . . ."
The contracting officer states that the Gentry decision is
distinguishable from the present case because Gentry's protest was
sustained due to the contracting officer's failure to comply with the PM
provisions relating to emergency contract solicitations, which are not at
issue here.
A protest conference was held on January 12, after which the protester
made its final submission, which restates its position as set out above
and emphasizes the following points:
-- In an internal memorandum of September 8, WEM had been considered an
incumbent along with Garrett and Lee; however, when the October 7
letters went out, only Garrett's and Lee's bids were solicited.
-- "Adding the Route to Garrett's contract would increase Garrett's
annual mileage from 246,512.16 to 848,250.97--an increase of 344
percent."
The protester asserts that the contracting officer's reliance on the
incumbency policy is misplaced because:
-- Since the incumbency policy was "neither a deviation to the
Procurement Manual, nor a part of the Procurement Manual, it cannot
serve as an exemption to the general policy of adequate competition
mandated by PM 1.7.1.a. Only another PM provision can alter the general
policies set out in the PM."
-- The "re-procurement" did not supply "additional
service" within the meaning of that term because it was in fact
"the wholesale re-procurement of a pre-existing, stand-alone
Route" -- one that is "more than three times the size of the
contract to which the Contracting Officer seeks to add it. The
definition of 'additional service' in the Incumbency Policy is not
reasonably susceptible of being read as permitting the allocation of a
large pre-existing, competitively procured route to a much smaller
route."
WEM argues that the contracting officer cannot rely on the limited
competitive procedures of PM 12.4.6 d.3 to justify his actions when his
statement "makes clear that he relied solely upon the Incumbency
Policy. . . ." The protester admits that the incumbency policy
"does not confer legally enforceable rights upon contractors,"
but argues that this office still has jurisdiction to determine whether
the policy "has been properly applied" and should be "wary
of embracing alternative interpretations of the PM that restrict
competition, particularly when no gainful purpose is served thereby."
WEM further contends that an independent justification for full
competition in this case is that the procurement "exceeds the scope
of Garrett's contract" because of the extent to which it increases
it, citing decisions of the Comptroller General[7] for
the proposition that a contract modification improperly exceeds the scope
of the contract when "the contract as modified is materially
different from the original contract for which the competition was
held." WEM lists as determinative of material difference "the
extent of any changes in the type of work, performance period, and costs
between the contract as awarded and as modified, as well as whether the
potential bidders reasonably would have anticipated the
modification," citing Neil R. Gross, footnote 7, supra.
Here, WEM asserts that in addition to the increase in mileage and
dollar value, Garrett's contract now has additional vehicle requirements
and an intermediate terminus. WEM contends that the PM also was violated
because the properly authorized individual did not approve a major service
change for Garrett's contract.[8]
WEM concludes that PM 12.4.12 c.(3) was violated because the
contracting officer did not sufficiently consider "factors that would
indicate the proper course of action to take in the best interests of the
Postal Service," including that the "route historically has been
served as a separate contract, and because there was competitive interest
in the Route." WEM requests that a regular solicitation be issued,
and that it be allowed to compete for this award "along with any
other prospective bidders."
Discussion
The protester argues in the alternative that the contracting officer
improperly relied on an expired and inappropriate incumbency policy, but
if the policy were held to be applicable, then WEM should have been the
rightful incumbent on the PDC - BMC route. WEM also contends that PM
12.4.6 d.3. does not apply to the circumstances of this case and that
there should have been a full and open competition. We address these
arguments in turn.
The incumbency policy attached to the June 1992 Special Transportation
Bulletin did not expire when the PM was revised in June 1993. Footnote 5, supra.
The incumbency policy was intended to be used together with PM 12.4.6
d.3., and, contrary to the protester's assertion, the contracting
officer's reliance on both in this case was proper. The guidance set out
in the incumbency policy is supplementary to and consistent with the PM's
guidance for limited competitive procedures.[9]
We lack jurisdiction to review the decision made by the contracting
officer to use limited competitive procedures involving modifications to
existing contracts instead of issuing a regular solicitation. Modification
of contracts is a matter of contract administration, which our protest
jurisdiction does not cover.[10] See Sodrel Truck
Lines, Inc.; Dennis Truck Line Co. of Ohio, P.S. Protest Nos. 92-01;
92-03, February 26, 1992. To the extent that WEM protests the election of
those procedures its protest must be dismissed. Id. However, the
protester is correct that we are authorized to examine the record to
determine whether limited competitive procedures (including the incumbency
policy) were properly followed in this case. We find that they were.
WEM cannot be an "incumbent" within the meaning of the
incumbency policy because its PDC - BMC route existed only as an emergency
contract.[11] Since the contracting officer decided to
issue contract modifications in this case rather than to award a new
contract, and emergency contracts may not be modified, PM 12.4.12 f., WEM
could not be considered for those modifications.
The protester's other arguments also fail. The PM does not state that
transportation services which previously had been the subject of a regular
contract route cannot now be the subject of a modification to another
existing contract under PM 12.4.6 d.3. Further, the PM does not limit the
amount of additional service to be added to a contract in miles,
compensation or equipment; and PM 12.4.12 c.1.(c)(3) specifically
authorizes major service changes through contract modification. Although
the Comptroller General decisions cited by the protester (footnote 7)
involved cases in which contract modifications exceeded the scope of
original contracts, and the protesters had standing because the remedy was
a new procurement for which they could propose, those decisions are not
applicable here because unlike the Postal Service, the agencies involved
had neither justification nor applicable procedures for limited
competition.[12] The record provides no basis to
overrule the use of limited competition or the incumbency policy in this
case.
The protest is dismissed in part and denied in part.
William J. Jones
Senior Counsel
Contract Protests and Policies
1. WEM, Inc., is a corporation owned by Mr. Willie E. Magno. Mr. Magno
holds the emergency contract which provides the basis for his protest in
his own name, not in the name of his corporation. For the purposes of
this protest, however, we will consider the corporation and its owner as
identical, and will refer to the protester as WEM.
2 . Procurement Manual (PM) 12.4.6 d. prescribes three procedures for the
acquisition of mail transportation services: competitive procedures,
noncompetitive procedures, and limited competitive procedures. PM 12.4.6
d.3. provides as follows:
Limited Competitive Procedures. With the approval of the next
higher-level of authority, contracting officers may solicit sealed bids
for additional service exclusively from contractors currently serving
common termini, providing service to the same intermediate points, from
contractors affected by Postal Service operational changes, or from
transportation companies with special security clearances.
Prior to July 1, 1992, the predecessor to this provision, then at PM
12.4.6 a.4, provided:
Limited Competitive Procedures. Contracting officers may solicit
sealed bids for additional service exclusively from contractors serving
common termini or providing service to the same intermediate points. . .
.
On June 3, 1992, the Office of Transportation & International Services
issued Special Transportation Bulletin No. 03-92, to which was attached
the "Incumbency Policy Statement," see footnote 4, and a deviation to
the Procurement Manual authorized by the Assistant Postmaster General,
Delivery, Distribution and Transportation Department, replacing the
previous text of PM 12.4.6 a.4 with the following, effective July 1,
1992:
Limited Competitive Procedures. Contracting [o]fficers may
solicit sealed bids for service exclusively from contractors currently
serving common termini, providing service to the same intermediate
points, or from contractors losing service due to Postal Service
operation changes.
That deviation remained in effect until the PM was revised on June 30,
1993, and the current section 12.4.6 d.3. was adopted. The protester
contends that the continued vitality of the deviation is of relevance to
this protest. We disagree, since each version of the limited competitive
procedure, even the original, allowed the restriction of competition to
contractors serving common termini, the class of contractors to which the
contracting officer limited the competition here.
3. The protester claims that it learned the basis for its protest "[o]n
or about November 4." Since the contracting officer has not alleged that
the protest is untimely, we consider it timely pursuant to PM 4.5.4 d.
and PM 4.5.4 e. Because WEM's protest was filed before Garrett's
contract modification was effective, WEM was awarded a new emergency
contract for service pending the resolution of its protest.
4 . The July 1, 1992, Incumbency Policy Statement addressed "the
allocation of additional service and newly structured service to current
Postal Service highway transportation contractors." It was "intended to
promote the fair and orderly procurement of newly structured service and
confers no legally enforceable rights upon the contractors." The
Overview to the policy statement stated, in part, that "[t]his policy
statement does not apply to Box Delivery contracts, emergency contracts
or contracts which have a non-postal facility as a terminus." [Emphasis
added.]
The policy statement contained definitions, including:
-- "Additional Service": additional trips of scheduled service
or service to additional facilities.
-- "Incumbent Contract":
[A]ny local contract which serves the exact same street addresses as
termini with the same equipment type as the additional service being
considered or any remote contract which serves the same metro area
termini with the same equipment type as the additional service being
considered.
The policy statement also contained the following general rules:
-- 2.1 "The holder of [an] incumbent contract MUST be offered any
additional service which serves the IDENTICALLY SAME [sic] . . . TERMINI
with the SAME EQUIPMENT TYPE as [is] currently served by the incumbent
contract . . . .
-- 2.4 "If more than one contract can be considered incumbent, the
contracting officer must determine which of the contracts best satisfies
the requirements of the additional services. . . . If the contracting
officer is able to determine that one incumbent contract best satisfies
the requirements of the additional service, the contracting officer must
add the additional service to that contract, if the negotiated price is
competitive."
[Emphases in original.] Further, if two or more incumbent contractors
equally satisfy the requirements, "all candidate incumbent contractors
will be allowed to submit a sealed bid for the additional service." The
service "will be added to the contractor who submits the most competitively priced bid."
5. The protester asserts that the incumbency policy has expired, because
the special transportation bulletin transmitting the policy states that
it will "remain in effect . . . until the Procurement Manual is
permanently revised" on June 30, 1993. The protester misreads the
bulletin, which clearly provided that it was the deviation to PM 12.4.6,
attached to the bulletin, which would remain in effect until the
Procurement Manual was revised, not the incumbency policy, also attached.
6. Also, PM 12.4.12 f. states: "The service and rate of compensation
under emergency contracts may not be changed unless specifically
authorized in the contract or by the next-higher level of contracting
authority."
7. Stoehner Security Services, Inc., Comp. Gen. Dec. B-248077.3, October
27, 1992, 92-2 CPD 285; and Neil R. Gross & Company, Inc., Comp. Gen.
Dec. B-237434, February 23, 1990, 90-1 CPD 212.
8 . WEM contends that the contracting officer never received the proper
higher level approval for using limited competitive procedures. It
asserts that the national manager of mail transportation purchasing did
not sign the approval; rather, a subordinate in his office signed for
him. "There is nothing in the record that shows that this authority is
delegable, or that it had been delegated."
The record shows that the request to add service and make a major service
change to Joe Garrett, Inc.'s contract was dated November 3, and was
approved November 7. Although a subordinate to the national manager
signed the authorization, she stated that she was signing "for" him. It
is routine for a subordinate to sign letters when the principal is
unavailable, and there exists no blanket prohibition against it. In any
event, we are not persuaded that the lack of the national manager's
signature on the approval dated November 7 confers any rights on this
protester.
9. MTPH 2.2.2.A., cited by the protester, also is
consistent with the PM and does not negate the incumbency policy. It
applies to situations--unlike this case--in which a regular transportation
solicitation will be issued.
10. While there is an exception when a modification is challenged as
outside the scope of the existing contract, M.L. Hatcher Pickup and
Delivery Service, Inc., P.S. Protest No. 77-25, July 29, 1977, this
exception does not apply here because, as discussed infra, the PM permits
the types of modifications made in this case. See also, COR, Inc., P.S.
Protest No. 90-16, June 22, 1990; Air Transport Association of America,
P.S. Protest No. 90-02, March 23, 1990.
11. The contracting officer's initial mistake in including WEM among
the incumbent contractors on the route in a September 8 internal
memorandum confers no rights on the protester.
12. The Gentry decision is also inapposite. Its facts did not involve
either the incumbency policy or PM 12.4.6 d.3. The decision held,
instead, that since emergency contracts are awarded through negotiation,
PM 12.4.6 b.4., the PM "requires that competitive emergency contract
solicitations be posted, and that copies of the solicitations be
furnished to the incumbent contractor and to anyone requesting the
solicitation." Id.
|