October 31, 1994
P.S. Protest No. 94-33
RICHARD C. GENTRY, INC.
Alabama Highway Mail Transportation Solicitations
Digest
Protest against failure to solicit incumbent contractor for emergency
service following nonrenewal of existing contracts is sustained;
Procurement Manual regulation requiring such solicitation is not
superseded by Mail Transportation Purchasing Handbook provision relating
to emergency contracts.
Decision
Richard C. Gentry, Inc., protests the contracting officer's
failure to solicit it for several highway mail transportation contracts.[1]
Gentry, a mail transportation contractor, had several box delivery
contracts out of the Gulf Shores, AL, post office, which were administered
by a contracting officer at the Southeast Area Distribution Networks
Office, Atlanta, GA (the DNO). The contracts expired by their terms on
June 30, 1994. Although the contracts contained provisions allowing for
their renewal for additional terms by mutual consent, the Postal Service
decided not to renew the Gentry contracts.[2] As allowed
by the contracts, Gentry sought review of the decision by the next higher
level contracting officer. By letter dated June 30 and addressed to Mr.
Gentry, that official, the Manager, National Mail Transportation
Purchasing, declined to overturn the contracting officer's decision.[3]
According to the protest, Ms. Gentry was advised by a DNO contract
specialist on June 8 that the Gulf Shores routes which had not been
renewed would be the subject of emergency solicitations. Ms. Gentry
requested copies of those "bid packages . . . plus any other routes
in [the] area." According to the protester, although the contract
specialist advised Ms. Gentry that Gentry "had the right to bid"
and "he would send [Gentry] all [the bid] packets when they were
available," he further stated that "'with things here as they
are now, I doubt you would be awarded a contract, even if you were low
bidder.'" The protest further recites that in response to Ms.
Gentry's inquiry why not, the contract specialist stated that he
"better not comment on that."
No solicitation packages were furnished to Gentry, and the Gulf Shores
contracts were awarded to others. The protester complains of its failure
to receive various specific solicitation packages[4] and
of the contract specialist's refusal to explain the basis for his
statement.
The contracting officer's statement sets out a different understanding
of the June 8 conversation, which it notes was initiated by Ms. Gentry.
According to the statement, the contract specialist understood Ms. Gentry
to have inquired generally whether Gentry would receive future highway
contract solicitations, without identifying any particular routes or
solicitations.[5] The contracting officer asserts that
the contracting specialist did not represent that Gentry would be
furnished any specific solicitations, but that if, as Ms. Gentry had
indicated, Gentry was on the bidder's list for the area, it would receive
notice of solicitations in the same manner as others on the list. However,
contrary to Ms. Gentry's representation, and unbeknownst to the contract
specialist, Gentry was not on the bidder's list for the area, and
accordingly, did not receive any solicitations in that fashion.
The protester has not responded to the contracting officer's statement.
Discussion
Procurement Manual (PM) 12.4.4 and 12.4.5 provide generally for the
maintenance of solicitation mailing lists and the publicizing of
solicitations by notice to individuals on the mailing lists and by
posting. The following portions of those sections are relevant here:
12.4.4 Solicitation Mailing Lists
a. Establishing Lists. The contracting officer must
establish a list of potential offerors for each
solicitation. . . .
12.4.5 Publicizing and Distribution of Solicitations
a. General. Solicitations for competitive procurements must
be distributed and publicized in accordance with the
requirements of this part 12.4.5. . . .
b. Solicitation Notice. A solicitation notice must be issued
for each solicitation, and must be posted in accordance
with paragraph d below. The solicitation notice must
describe the service and equipment requirements, summa
rize applicable qualification requirements, state the date
and time set for receipt of bids or proposals, and tell
how to obtain the complete solicitation package.
* * *
d. Posting.
1. A solicitation notice must be posted for a minimum
of 30 days before the date for receipt of bids or
proposals unless precluded by urgency. In case of
urgency, the notice must be posted for a minimum
of 15 days . . . .
* * *
e. Distribution. The contracting officer must mail the
solicitation, or a solicitation notice, to all potential
bidders or offerors on the solicitation mailing list. .
The complete solicitation package must be mailed to
(1) any incumbent contractor, whether that contractor is
performing on a regular, temporary, or emergency contract;
. . . (3) those requesting the solicitation in response
to a notice of availability. For treatment of concerns
that are debarred, suspended, or ineligible,
see 3.3.2 d.[6]
These provisions apply equally to advertised and negotiated contracts
as shown by the use of terms such as "bids" and
"proposals" in the alternative. They provide for an exception
for urgency only with respect to posting, allowing a limitation on posting
to fifteen days. Emergency contracts are "awarded through competition
and negotiation" or noncompetitive negotiation. PM 12.4.6 b.4.
Accordingly, the Procurement Manual requires that competitive emergency
contract solicitations be posted, and that copies of the solicitations be
furnished to the incumbent contractor and to anyone requesting the
solicitation.
The contracting officer's reliance on the Mail Transportation
Procurement Handbook to the contrary is misplaced. While MTPH 6.2.1 A.
provides for oral or written solicitation and directs contracting
personnel to "[c]ontact as many prospective offerors as possible to
encourage competition" before it notes that "[c]ircumstances
permitting, you should solicit proposals from a minimum of three
offerors" (emphasis in original), it does not purport to alter or
amend the requirements of PM 12.4.5 and 12.4.6.[7]
Kessler, supra, involved the contracting officer's failure to solicit
an incumbent contractor with respect to replacement emergency service
following the Postal Service's termination of Mr. Kessler's contract for
convenience. The Postal Service and Mr. Kessler had failed to reach
agreement on the terms of a contract modification which would have reduced
both the time of a daily trip and Mr. Kessler's compensation. The
contracting officer explained that during the negotiations prior to the
termination for convenience, Mr. Kessler had expressed concern that he
could not safely perform the proposed reduced schedule; accordingly, the
contracting officer concluded that Mr. Kessler could not perform the same
schedule set out in the emergency contract and declined to solicit him for
the service. The decision noted that the contracting officer's conclusion
was a determination that Mr. Kessler was not a responsible offeror for the
replacement service, and that "it was premature and prejudicial to
Mr. Kessler for the contracting officer to make that determination solely
on the basis of the [previous] discussions," since Mr. Kessler might
have changed his view once he understood the Postal Service's firm
intention to solicit on the basis of the revised schedule.
Kessler distinguished its situation from one in which a defaulted
contractor might properly be excluded from a reprocurement,[8]
and also noted that a previous decision, Crist Trucking, Inc., P.S.
Protest No. 76-12, May 11, 1976, had condoned a contracting officer's
failure to solicit, for emergency service, an offeror whose "large
number of irregularities on two currently operated routes caused [the
contracting officer] to question the offeror's ability to provide the
emergency service." Kessler described the "evidence before the
contracting officer [in Crist]" as "far more substantive than
the evanescent concerns available here." Crist, however, involved a
case in which the then applicable procurement regulation, the Postal
Contracting Manual (PCM), explicitly excepted solicitations for emergency
service from the publicizing requirements applicable to other mail
transportation contracts. That decision also noted the contracting
officer's representation that the excluded offeror would be allowed to bid
on the solicitation for permanent service which would follow the emergency
service from which it was excluded. Given these distinctions from this
case, Crist does not govern its result.
Accordingly, we conclude that the contracting officer erred in failing
to solicit Gentry, the incumbent contractor, with respect to the
replacement service in Gulf Shores. It is less clear whether Ms. Gentry's
general request for other solicitations in the area was specific enough to
require Gentry's solicitation for that service. In view of the relief we
direct below, however, we need not resolve the matter.
The emergency service which was solicited was of short duration; we can
perceive little benefit to the protester and substantial disruption to the
Postal Service were we to direct the termination and resolicitation of
that service. Instead, the protester may be afforded appropriate relief by
our direction to the contracting officer to reinstate Gentry on the
solicitation mailing lists maintained pursuant to PM 12.4.4; to solicit
Gentry for subsequent emergency service sought within areas for which it
expresses interest; and to post solicitation notices for all emergency
service solicited within its service area as required by PM 12.4.5 d. or
seek an appropriate deviation from the posting requirement in accordance
with PM 1.4.
Gentry's eligibility for award with respect to any solicitation on
which it otherwise is found to be the low responsive bidder or the most
advantageous offeror will, of course, require an appropriate determination
of its responsibility in that case. PM 3.3.1 a. Such determinations must
be made case-by-case on the facts relevant to the individual solicitation.
The protest is sustained to the extent indicated.
William J. Jones
Senior Counsel
Contract Protests and Policies
1. Richard C. Gentry, Inc., is a corporation whose officers include
Richard G. Gentry and Sandra S. Gentry. In this decision, "Gentry" refers
to the corporation, while "Mr. Gentry" and "Ms. Gentry" refer to its
principals.
2. The exact date that Gentry was informed of the nonrenewals is not
evident from the protest file.
3 . The letter included the following explanation for that decision:
As I have reviewed the file, it has become clear to me that route
operations have experienced periodic problems with the quality of
service provided by you or your employees. This includes the incorrect
delivery, delay, and destruction of mail. We have received numerous
Contract Route Irregularity Reports (PS 5500s) regarding your failure to
follow the instructions of the Postmaster. The file also indicates that
you have been confrontational with the Postmaster, causing disruptions
at the Gulf Shores Postal Facility. The Postal Service is heading in a
new, and hopefully better, direction through teamwork between mangers,
personnel, and vendors. We simply cannot tolerate confrontational and
intimidating behavior in the Postal workplace.
4 . The protest identifies three communities in addition to Gulf Shores for
which it wished to propose: Lillian, Elberta, and Foley, AL. The
contracting officer has identified five solicitations involving those
communities; an advertised solicitation for service in Lillian issued April
15 and for which bids were due May 24, and emergency solicitations for
service in Gulf Shores issued June 9 and in Foley and Elberta each issued
June 7. Written offers on the emergency solicitations were due June 20.
We find no merit in Gentry's protest with respect to the Lillian solicitation,
since that solicitation was issued and bids were received well prior
to Ms. Gentry's request for solicitations. Accordingly, the remainder of
this decision deals only with the emergency solicitations.
5 . The contract specialist makes a distinction between ordinary
solicitations, in which prospective contractors who have indicated an interest in
solicitations within a specific area receive notice of the availability of
a solicitation and may request it, and emergency solicitations, for which
the DNO furnishes copies of the solicitation to specific offerors.
According to the statement, the contract specialist understood Ms. Gentry's
inquiry to relate only to the former procedure, and not to the latter.
The contract specialist was responsible for establishing a list of
prospective offerors for the replacement service in Gulf Shores. It was
not his intention to include Gentry among those offerors, and he did not
volunteer to furnish Gentry copies of those solicitations.
The contracting officer asserts that the Mail Transportation Procurement
Handbook provides for the solicitation of emergency service either orally
or in writing from at least three potential contractors, and notes that
time is of the essence in such awards. Accordingly, the contracting
officer believes it "implicit" in the emergency contracting procedures that
he "solicit . . . offers [only] from responsible offerors. . . . In this
instance, given Mr. Gentry's unacceptable . . . behavior toward . . .
Postal employees, I would not have found Gentry to be a responsible
offeror."
6. PM 3.3.2 d.2. provides, in part, that "[c]ontracting officers may not
solicit proposals or quotations from [or] award contracts to" debarred or
suspended contractors.
7 . Nor could it. PM 12.1.1 b. notes that the MTPH provides "[p]rocedural
guidance to implement and supplement" PM Chapter 12. And MTPH Transmittal
Letter 2, February 1, 1990, notes:
The MTPH is intended as a companion volume to the Procurement Manual
(PM). The PM contains policy guidance and a few mandatory procedures;
the MTPH translates that guidance into practices applicable to
transportation services procurement. . . . [Contracting officers and
their staffs] should keep in mind the following points:
- The PM and the MTPH go hand in hand. . . Both books must be
consulted to fully understand any aspect of the procurement process.
A previous decision of this office, Melvin R. Kessler, P.S. Protest No. 90-36,
October 23, 1990, reached the different conclusion that PM 12.4.5 e.,
requiring the solicitation of incumbent contractors for replacement
service, applied to solicitations "for permanent highway transportation
service," but did not apply to emergency service, citing MTPH 6.2.1. Upon
further consideration, we believe this aspect of Kessler was decided
incorrectly for the reasons set out herein.
8. Citing Jack Yanks Construction Co., P.S. Protest No. 75-56. August 13,
1975.
|