September 2, 1994P.S. Protest No. 94-31H. J. CORBIN
Solicitation Nos. 608-6019-94 and 608-6039-94
On Reconsideration
Mr. H. J. Corbin requests reconsideration of portions of this office's decision dismissing in part and denying in part his protest against the award of two mail transportation contracts to Mr. Louis E. Shorter. H. J. Corbin, P.S. Protest No. 94-31, August 4, 1994.
Mr. Shorter submitted four bids under two names under solicitations 608-6019-94 (solicitation -19) and 608-6039-94 (solicitation -39). One of the bids, intended for solicitation -19, was misidentified on the envelope as being for solicitation -39. When that bid was opened, the contracting officer determined that the misidentification of the solicitation number was a minor informality, and considered that bid in connection with and entered it on the abstract of bids for solicitation -19.
The decision concluded that Mr. Corbin lacked standing to protest the award to Mr. Shorter under solicitation -19 because his objections to the award, if sustained, would not entitle him to the award. With respect to solicitation -39, the decision concluded that Mr. Shorter's submission of multiple bids was not improper; that the exclusion of the bid intended for solicitation -19 from the competition under solicitation -39 was proper; and that the contracting officer properly could accept the lower of Mr. Shorter's two bid bids on that solicitation, although he had excluded the lower of Mr. Shorter's two bids on solicitation -19 because award on the basis of that bid would have been unfair to the bidder. Mr. Shorter's lower bid on solicitation -39, unlike his lower bid on solicitation -19, was not out of line with the other bids received.
The request for reconsideration was received by this office on August 19. A "supplement" to that request dated August 18, but postmarked and accompanied by a letter dated April 23, was received August 25.
The initial request for reconsideration makes several points, which we summarize as follows:
DiscussionOur review of requests for reconsideration is limited.
Federal Properties of R.I., Inc., On Reconsideration, P.S. Protest No. 93-02, July 9, 1993, quoting Fort Lincoln New Town Corporation, On Reconsideration, P.S. Protest No. 83-53, November 21, 1983 (citations omitted).
To the extent that the protester contends that Mr. Shorter's bids contained an erroneous taxpayer identification number, that the submission of multiple bids made the bids nonresponsive, or that it was improper for the contracting officer to consider both bids because the later bid should have replaced the former one, he is repeating contentions previously made in the course of the protest.[2] To the extent that he is contending that the contracting officer misapplied the regulations applicable to the correction of mistakes, he is raising a new matter which cannot now be considered.[3]
The remaining issue, the misdating of Mr. Shorter's bid on solicitation -39, may have been based on information not available to the protester until he received the protest decision. The protester is correct that Mr. Shorter could not have submitted a bid on April 4 for a solicitation which was not issued until April 20. We conclude, however, that the April 4 date (it was actually expressed as "4/4/94") was a correctable "clerical mistake apparent on the face of the bid" since the page on which the date appeared also included, in the bidder's hand, the correct solicitation number and the April 20 solicitation date, providing clear evidence that the bid followed the solicitation.
The request for reconsideration is denied.
William J. Jones Senior Counsel Contract Protests and Policies
1. The cited decision, Russell Drilling Co., Comp. Gen. Dec. B-218577, 85-2 CPD 87, July 25, 1985, deals with the strict requirement that when a bidder seeks to correct an error in its bid and the bid, as corrected, would displace another bid, both the error and the intended bid price must be evident from the face of the bid. Procurement Manual (PM) 12.7.6. b.3.(a)(3) is to the same effect. However, neither the decision nor the regulation has application to the situation at issue here, in which there was no claim of a mistake in a bid price which would have displaced a lower bid.
2. We note, however, contrary to the protester's contention, that the completion of a taxpayer identification clause is a matter pertaining to a bidder's responsibility, and not to the responsiveness of the bid. Accordingly, "the failure of a bidder to properly complete such items may be corrected after bid opening." Nomura Enterprise Inc.--Reconsideration, Comp. Gen. Dec. B-244993.2, 91-2 CPD 322, October 9, 1991.
3. It is difficult to understand the protester's contention in this respect. The contracting officer took no action under the mistake regulations with respect to Mr. Shorter's bids on solicitation -39, instead accepting the lower of the two bids which Mr. Shorter submitted.
|