Date: August 8, 1988P.S. Protest No. 88-37DRY STORAGE CORPORATIONSolicitation No. 169990-88-A-0013DECISIONDry Storage Corporation (Dry Storage) protests the contracting officer's determination that its bid under Invitation For Bids No. 169990-88-A-0013 (the IFB) was nonresponsive. The IFB, issued by the Central Procurement & Material Management Service Center on May 5, 1988, sought bids for warehouse services within the DuPage County and Cook County geographical area. Section A-3 of the IFB contained the following pricing schedule:
Three bids were opened on May 27. The Abstract of Bids Received recorded Dry Storage's bid as $51,650 per month, Morrison-Knudsen Services as $20,151.80, [Morrison-Knudsen Services bid was rejected because its warehouse was not located within the geographical area required by the IFB. ] and New Breed Transfer Corp., the intended awardee, at $41,500. The contracting officer considered Dry Storage's bid nonresponsive based on the additional sheet which it attached to the IFB. Dry Storage inserted prices for all blank lines and inserted beneath the estimated monthly quantity of 250 CWT for sub-item b the words "25,000 Shipment". One page before the pricing schedule, Dry Storage attached a new page to the IFB, which stated:
In addition, Dry Storage submitted a cover letter to its bid, and stated that its warehouse was a "high-cube/high-density racked building." Dry Storage further stated:
By letter of June 2, the contracting officer advised Dry Storage that its bid was considered nonresponsive and would not be considered for award. Dry Storage responded by letter of June 3, contending that it had attempted to provide a firm bid, and that it had hoped if its bid were not understood that it would be so informed and given a chance to explain the details inserted in its proposal. Dry Storage contended that the additional sheet attached to the IFB was provided "in the hope that some of the items, which were not easily understood in your request, could be identified as potential 'misunderstandings'." Dry Storage then addressed the areas which the contracting officer considered to be nonresponsive. In the same letter, Dry Storage revised its bid price. Dry Storage stated that its bid for handling charges was based upon 100 shipments per month of items weighing 25,000 pounds each. Dry Storage stated that it had mistakenly assumed that each shipment was going to be 25,000 pounds, though it now appeared that monthly volume would be 100 shipments of items weighing 250 pounds each. Dry Storage thus revised its bid price to a total monthly cost of $35,067.50, which would have displaced New Breed Transfer Corp.'s low bid of $41,500 per month. Dry Storage stated that it considered the exclusion of its bid unfair and that it believed its bid should not have been disqualified. The contracting officer treated Dry Storage's June 3, letter as a protest and referred it to this office pursuant to Postal Contracting Manual (PCM) 2-407.8(e). The contracting officer also submitted a report to this office addressing the points raised by the protester. The contracting officer properly rejected Dry Storage's bid as nonresponsive. The test of responsiveness is:
Sensory Electronics, Inc., P.S. Protest No. 87-124, January 21, 1988; Data Switch Corporation, et al., P.S. Protest Nos. 85-4, 85-5, April 29, 1985. The responsiveness of a bid must be determined from material available at bid opening; post-opening explanations cannot be considered to correct a nonresponsive bid, even if a lower price could be obtained by accepting the corrected bid. Pease Management and Construction, Inc., P.S. Protest No. 86-68, October 24, 1986. In determining responsiveness, we look at the legal obligation to perform according to the terms of the IFB, and not the bidder's current willingness to perform. See Mattox Motor Service, P.S. Protest No. 83-36, August 12, 1983. This rule maintains the integrity of the competitive bidding system by treating all bidders fairly and not allowing any contractor "two bites" at the apple after bid opening. Government Contract Services, Inc; Daly Construction, Inc., P.S. Protest No. 85-95, January 21, 1986. With these principles in mind, clearly Dry Storage's bid is nonresponsive. The pricing schedule advises bidders that the price for the monthly storage rate "must be billed only for floor space actually occupied by Postal Service equipment." The IFB states that an estimated monthly quantity of 25,000 square feet of floor space will be required. Dry Storage's attached "Preparation of Rates" sheet states that its storage rate is based on using "approximately 12,500 square feet for storage and 12,500 feet for aisles, etc." The cover letter accompanying Dry Storage's bid also states that because of the height of its warehouse, it could store in 12,500 square feet of occupied floor space what normal warehouses store in 25,000 square feet of occupied floor space. The contractor's bid price is thus a price for only 12,500 square feet of actually occupied storage space. [The contractor could not properly assume that, because its warehouse permitted double-stacking, its quote for one-half the area of occupied floor space would be acceptable. The contract - ing officer advises that some of the equipment which was to be stored may not lend itself to stacking or palletization. ] The IFB, however,requested a price for 25,000 square feet of actually occupied storage space. Because the contractor did not submit a price for 25,000 feet of actually occupied floor space, its bid was properly rejected as nonresponsive. [Since we find Dry Storage's bid nonresponsive on this basis, there is no need to reach the other issues in the protest.] Although Dry Storage's cover letter requested the contracting officer to inquire if he had any questions as to its bid, such inquiry would not have been permissible since it would have provided Dry Storage with "two bites" at the apple. The protest is denied.
|