April 11, 2008
Appeals of
FRANK BAIAMONTE
PSBCA Nos. 5297 and 5324
Under Contract No. HCR 863C5
APPEARANCE FOR APPELLANT:
Frank Baiamonte
APPEARANCE
FOR RESPONDENT:
Gary Shapiro, Esq.
Office of the General Counsel
United States Postal Service
OPINION OF THE
BOARD
Respondent, United States Postal Service, terminated its contract with
Appellant, Frank Baiamonte, for delivery of mail to
cus
The appeals were consolidated and, at the election of the parties, are
being decided on the record without an oral hearing in accordance with 39 C.F.R.
§955.12. Both entitlement and
quantum will be addressed (Order,
FINDINGS OF
FACT
1. On
2. The
3. The contract required
Appellant to deliver all mail tendered to him:
“The supplier [Appellant] shall carry all
mail tendered for transportation under this contract, whatever may be its size
and weight, with certainty, celerity, and security, in accordance with the
operating schedule and between the points fixed in the schedule, as modified
from time to time pursuant to this contract.”
(AF 38, Contract Clause B.3.a, Sanctity of
the Mail (p. 180); see Contract Clause B.3.j (3)).
4. The contract included a
Claims and Disputes clause describing the process for submission and resolution
of claims and authorizing Appellant to appeal final decisions of the contracting
officer. The clause required that
Appellant “proceed diligently with performance of this contract, pending final
resolution of any request for relief, claim, appeal, or action arising under the
contract, and comply with any decision of the contracting officer.” (AF 38, Contract Clause H.2, CLAIMS AND
DISPUTES (Clause B-9) (January 1997)).
5. The contract’s
Termination for Default clause authorized Respondent to terminate the contract
if Appellant failed to complete the requirements of the contract within the time
specified in the contract or, after receiving notice and at least three days to
cure, failed to perform any other provision of the contract (AF 38, Contract
Clause H.4, TERMINATION FOR DEFAULT (Clause B-13) (January 1997)
(Modified)).
6. In the Events of Default
clause, the contract identified grounds that would justify termination under the
Termination for Default clause.
These included Appellant’s failure to perform service according to the
terms of the contract and failure to follow the instructions of the contracting
officer. (AF 38, Contract Clause
H.5, EVENTS OF DEFAULT (Clause B-69) (January 1997)).
7. The contract authorized
Respondent to acquire similar, replacement services after a termination for
default, “and the supplier [Appellant] will be liable to the Postal Service for
any excess costs.” (AF 38, Contract
Clause H.4, TERMINATION FOR DEFAULT (Clause B-13) (January 1997) (Modified),
subsection b).
8. Appellant questioned the
authority of the Cottonwood Post Office Cus
9. In a
10. By letter dated
11. On March 1, Appellant
faxed a letter to the contracting officer claiming that the formal conference
and the alleged deficiencies that led to it were in retaliation for complaints
he had made about the management of the Cottonwood Post Office (AF
22).
12. The postmaster convened
the formal conference on
13. On
14. Postal Service Handbook
P-5, Highway Contract Routes – Box Delivery Service, at section 134.242,
instructs post offices administering box delivery contracts, such as
Appellant’s, to monitor the times the contractor reports for duty, leaves the
post office for his route, and returns to the post office. The Handbook permits use of monitoring
devices for this purpose. (AF
15).
15. In May 2005, the
Cottonwood Post Office implemented use of a time clock to record mail delivery
contractors’ arrival and departure times (AF 15; Langford Decl. ¶14).
Appellant objected and, on
16. By letter dated
17. On
18. Appellant opposed the
proposed service change. In an
August 9, 2005 letter to the Manager, Transportation Contracts (the contracting
officer’s superior at the Pacific Area Distribution Networks Office (“DNO”)) and
the manager of transportation services at the Phoenix Processing and
Distribution Center, Appellant stated his opposition to the service
adjustment. Appellant contended
that the route adjustment was unnecessary.
(AF 7, 10).
19. Appellant called the
Manager, Transportation Contracts, frequently during the period June through
September 2005, complaining about matters in the Cottonwood Post Office, and
stating that he did not accept the authority of the
Cus
20. As part of the route
realignment effort, the DNO prepared a solicitation dated
21. On
22. Appellant refused to
deliver the solicitation notices.
At least twice the Supervisor gave Appellant direct orders to deliver
them, and each time Appellant refused.
In doing so, Appellant was yelling, was argumentative and was disturbing
and upsetting to a number of other contractors and employees in the post
office. The Supervisor directed
Appellant to go to the postmaster’s office to discuss it away from the workroom,
and Appellant loudly and defiantly refused to go. He left to deliver his route without
taking the solicitations. (AF 3, 4;
Declaration of B. Boudreau ¶2 and Exhibit A (AF 41); Declaration of L. Boudreau
¶2; Declaration of N. Duke ¶2; Declaration of C. McKinney ¶2; Rachel Decl. ¶11; Langford Decl. ¶¶ 18,
19).
23. After being advised of
Appellant’s refusal to deliver the solicitations (AF 42), the Manager,
Transportation Contracts, called Appellant. He advised Appellant that he was
required to deliver the solicitations and to follow instructions of the
24. The
25. A Transportation
Contract Specialist in the Pacific Area Office promptly contacted Cottonwood
Post Office management for names of potential replacement contractors. She contacted eight potential
contractors and received telephonic offers from four of them to supply emergency
service on Appellant’s route.
Respondent accepted the lowest offer, $55,000 per year, which was lower
than an internal Postal Service estimate, and awarded a replacement contract in
that amount. The service procured
was exactly the same as that provided under Appellant’s contract, except that
the size of the required vehicle was reduced from 80 to 65 cubic feet, a change
that had no effect on price.
(O’Keefe Decl. ¶13; Declaration of A. Arana (“Arana Decl.”) ¶¶2-7 and Exhibits A-C).
26. For the period September
9 through 30, Respondent calculated its daily excess transportation costs as the
difference between the annual cost of the replacement contract ($55,000) and
Appellant’s contract rate at the time of termination ($47,302.35) divided by
365. For 22 days at $21.09 per day,
the excess costs incurred by Respondent were $463.98 through the end of
September. (Arana Decl. ¶¶8-10 and Exhibits D,
E, F).
27. Effective
28. Respondent incurred
administrative costs associated with soliciting and contracting for the
replacement service. These costs
were the hourly cost for secretarial and contract specialist time (4 hours and
10.3 hours, respectively), resulting in administrative costs of $325 (O’Keefe
Decl. ¶13; Arana Decl. ¶9 and Exhibit E).
29. On
30. Appellant’s timely
appeal of the November 3 final decision was docketed as PSBCA No. 5324 (Notice
of Appeal dated
DECISION
Termination for
Default, PSBCA No. 5297
Respondent argues that Appellant’s refusal to follow instructions given
him by the Cottonwood Post Office management and his refusal to deliver First
Class Mail justify the termination for default of Appellant’s contract. On
Appellant argues that under the
contract he should have been given a cure notice and at least three days to cure
any deficiencies in his performance before the termination (Finding
5). However, Appellant’s
refusal to deliver First Class Mail was a material failure to perform the
requirements of the contract. Under
such circumstances, the Termination for Default clause does not require that
Respondent first give Appellant an opportunity to cure (Finding 5). See Geo-Marine, Inc. v. General Services
Administration, GSBCA No.
16247, 05-2 BCA ¶ 33,048 at 163,830.
Additionally, Appellant’s refusal to follow the instructions of the
Cus
Appellant contends he was not given notice and an opportunity to cure as
required by the contract before being terminated on this ground. The evidence in the record is
otherwise. The contracting officer
directed Appellant orally and in writing to follow the oral or written
directions of the postmaster and his designee. She provided an adequate opportunity to
cure when she advised on
Moreover, Appellant’s unequivocal statement to the Manager,
Transportation Contracts, that he would not deliver the solicitations in
question and that he would not follow instructions of the Cottonwood Post Office
Supervisor (Finding 23) obviated any need for a formal cure notice. See Todd’s Letter Carriers, PSBCA Nos. 4904, et al., 05-2 BCA
¶ 33,121 at 164,135; P Star, Inc., PSBCA No. 4839, 04‑1 BCA
¶ 32,514 at 160,840.
As Respondent has demonstrated ample grounds for terminating Appellant’s contract for default, the burden shifts to Appellant to present evidence of excusable causes for his failure to perform, Pamela J. Sutton, PSBCA No. 1622, 88‑3 BCA ¶ 21,031 at 106,237, or to show that the termination was an abuse of the contracting officer’s discretion, Patricia J. Stevens, PSBCA No. 3272, 94-1 BCA ¶ 26,419, recon. denied, 94-2 BCA ¶ 26,951.
Appellant argues that the termination resulted from a conspiracy among
Respondent’s employees and mail delivery contractors in the Cottonwood Post
Office to get rid of him. He
submitted witness declarations he contends demonstrate the existence of such
conspiracy. However, Appellant’s
witnesses do not address the matters at hand: Appellant’s refusal on
Appellant argues that the contracting officer’s failure to provide him notice of her intention to terminate his contract and an opportunity to respond denied him his rights to due process under the Constitution. As discussed above, such notice was not required by the contract under the circumstances of Appellant’s termination. Additionally, Appellant has had an opportunity in this proceeding to raise any excuses or explanations for his refusal to deliver First Class Mail, thus satisfying his due process rights. See Patricia J. Stevens, PSBCA No. 3272, 94‑1 BCA ¶ 26,419, recon. denied, 94-2 BCA ¶ 26,951; Melvin R. Kessler, PSBCA Nos. 2820, 2972, 92-2 BCA ¶ 24,857 at 123,997, aff’d on recon., 92-3 BCA ¶ 25,092; Shorthaul Trucking Co., PSBCA No. 1046, 1985 WL 16706 (P.S.B.C.A.), June 18, 1985.
Bad
Faith
Appellant
alleges that the termination of his contract was in retaliation for his
initiation of an Equal Employment Opportunity proceeding and contacting the
Inspection Service regarding management of the Cottonwood Post Office. He contends that his mistreatment by
Respondent’s employees and contractors demonstrated that the termination of his
contract was the product of bad faith.
The record does not support Appellant’s allegations. While substantial friction existed
between Appellant and a number of Respondent’s employees and contractors during
contract performance, that does not prove bad faith on Respondent’s part. See IMS Engineers -
Architects, P.C., ASBCA No. 53471, 06-1 BCA ¶ 33,231 at 164,674,
recon. granted in part and otherwise denied, 07-1 BCA ¶ 33,467. Appellant has not shown by clear and
convincing evidence that Respondent’s officials acted maliciously or with intent
to harm Appellant, which showing is required to sustain a finding of bad
faith. See Am-Pro
Protective Agency, Inc. v.
Other Grounds for
Termination
Respondent
raised other grounds as justifying the default termination: Appellant’s alleged performance
deficiencies, disruptive and threatening conduct, improperly overstating the
number of deliveries on his route to inflate his pay, and misrepresentation of
his and his assistant’s criminal history on contractor security screening
questionnaires. Because we have
found the termination justified by Appellant’s refusal to deliver First Class
Mail and refusal to follow instructions of Respondent’s authorized official, we
need not address those other grounds for the termination or the arguments and facts offered by the
parties regarding them.
Reprocurement Costs,
PSBCA No. 5324
The contract
authorized Respondent to “acquire similar supplies or services” after a default
termination and provided that Appellant “will be liable to the Postal Service
for any excess costs.” (Finding 7). Respondent has demonstrated that the
services procured via the replacement contract were the same as those required
by Appellant’s contract and that Respondent acted reasonably in soliciting and
awarding the emergency contract (Finding 25). Respondent incurred reasonable
administrative costs associated with the reprocurement as well as excess costs
of providing the service for a total of $1,144.30 (Findings 26-29). These circumstances plus Respondent’s
limit of the reprocurement costs to just 106 days of the remaining term of the
contract—the contract had about nine months left to run—constitute a prima facie
showing of adequate mitigation of the reprocurement costs Respondent
incurred. See Benjamin
Mullins, PSBCA Nos. 5136, 5173, 05-1 BCA ¶ 32,918; Don Wasylk d/b/a Klysaw, PSBCA
Nos. 4186, 4283, 00‑1 BCA ¶ 30,844; Steve Neill, PSBCA Nos. 4004,
4005, 98-2 BCA ¶ 29,837.
Appellant has not presented evidence to challenge Respondent’s mitigation
of damages, its calculation of its claimed reprocurement costs, or the
administrative costs charged to Appellant.
Thus, Respondent has shown entitlement to recover its excess costs of
reprocurement in the amount of $1,144.30.
The appeals are denied.
Norman D.
Menegat
Administrative
Judge
Board
Member
I concur:
I concur:
William A.
Campbell
David
Administrative
Judge
Administrative Judge
Chairman
Vice Chairman
[1] In his letter, the
successor contracting officer gave Appellant credit for $777.57 he believed had
been withheld from funds earned by Appellant before the termination but not paid
to him. However, the contracting
officer’s assumption that Respondent had withheld $777.57 from money due
Appellant was in error. In fact,
Respondent had paid Appellant the $777.57 in late September, so any credit was
unwarranted. (SAF 2C; See
Appellant’s Brief to Order Dated March 16, 2006, p. 3).