October 31, 2007
PSBCA No. 5404
Appeal of
CEPHRUS DEVORE
Under Contract No. 475630-01-P-0670
APPEARANCE FOR APPELLANT:
Berta E. Nichols, Esq.
APPEARANCE FOR RESPONDENT:
William J. Trumpbour, Esq.
Office of the General Counsel
United States Postal Service
OPINION
OF THE BOARD
Appellant, Cephrus Devore, has filed
a timely appeal from a contracting officer’s final decision denying his claim
arising from the termination of his cleaning services contract. A hearing in this matter was held in
FINDINGS OF FACT
1.
On August 27, 2001, Respondent, United States Postal Service, and
Appellant entered into contract No. 475630-01-P-0670 requiring Appellant to
provide cleaning services at the Ridgeland, South Carolina Post Office for the
period September 8, 2001, through September 5, 2003. As a result of bilateral modifications in
2003 and 2005, the contract period was extended to
2.
The contract required Appellant to perform various types of cleaning
services, Monday through Saturday, each week (AF 1, pp. 15-23).
3. The
Ridgeland Postmaster (postmaster) was designated as the Contracting Officer’s
Representative (COR) (Transcript of Hearing, Pages (Tr.) 58, 60) and, as such, was
responsible for the day-to-day administration of the contract (AF 1, p. 6).
4. As part of its terms and conditions, the
contract contained a Failure to Perform Work clause, which provided that for
each day Appellant failed to perform the required cleaning services, his
contract payment would be reduced by 1/312 of the annual amount. Based on the annual rate at the time the
contract was terminated, this would result in a deduction of $76.12 for each day
of work missed. The clause also provided
that “[c]ontinued failure to perform may be cause for termination of the
contract.” (AF 1, p.
4).
5.
The contract also included a Termination on Notice clause that included
authority for Respondent to terminate the contract on one day's written notice
if in the contracting officer’s judgment Respondent's best interest required
such action. It also provided that
either party could terminate the contract upon 30 days' written notice with no
liability except payment for actual services rendered. (AF 1, p. 6).
6.
Under the contract's Supplier Screening Requirements clause, any
employees or subcontractors used by Appellant who required access to the
Ridgeland Post Office for a period in excess of two weeks were required to
undergo screening and be approved by either the contracting officer or the COR before
being allowed access to the post office.
It was Appellant's responsibility to obtain the necessary clearance. (AF 1, p. 8; Tr. 42; Respondent’s
Exhibit 1, p. 3).
7.
The solicitation for the contract contained attachment 4, entitled,
“Performance and Evaluation Factors” (PEF form) on which Appellant listed the
names and cleaning qualifications of two substitutes who could perform the work
in Appellant’s absence (AF 1, p. 25). Although
not communicated to Appellant, the contracting officer’s practice at the time
of award was to permit those individuals listed on the PEF form as substitutes. To add additional names to the approved list
of substitutes after contract award, the contracting officer’s practice
required suppliers to complete another copy of the PEF form. (Tr. 37-38).
8. For two days in 2002, Appellant was
accompanied while he performed by Mr. R. Davis, who he wished to have work as
his substitute. Mr. Davis was not one of
the two substitutes previously listed by Appellant on the PEF form. Appellant introduced Mr. Davis to the postmaster
and advised that he was to be Appellant's substitute in the event Appellant was
unavailable to perform his duties under the contract. (Tr. 55, 80). Based on Mr. Davis being allowed to accompany
him on those two days and his conversation with the postmaster, Appellant
believed that the postmaster had approved Mr. Davis as a substitute (Tr. 55, 58,
80). Appellant never completed the forms
required to obtain clearance for Mr. Davis (Tr. 56-58) nor did he submit for
the contracting officer’s approval an updated copy of the PEF form listing Mr.
Davis as a substitute (Tr. 38).
9.
On one occasion between 2002 and 2004, Mr. Davis substituted for
Appellant during a two to three day period when Appellant was out of town (Tr. 64,
65; Joint Notice Report Tab 8, 1(c)).
10.
On
11.
On Friday, September 15, 2006, Mr. Davis arrived at the Ridgeland Post
Office and performed cleaning services on behalf of Appellant (Tr. 23, 86). The postmaster was on vacation at the time Mr.
Davis performed these cleaning services (Tr. 81). Although the contract required Appellant to
perform cleaning services on Saturdays, Mr. Davis did not report to the Ridgeland
Post Office on
12.
On
13.
On
14. Appellant was released from the
15. On
16. On
17. On
18.
By letter dated
19.
By final decision dated
20.
In his post-hearing brief, Appellant reduced the amount of his claim to
$5,480, which is the amount Appellant alleged he was entitled to for the period
from September 15, 2006 (the day after his incarceration) through December 4,
2006 (the day Appellant claims the termination became effective).
DECISION
Appellant argues that he is entitled
to additional payment because Respondent breached the contract by preventing his
substitute from performing cleaning services during the period Appellant was
unavailable. Appellant also argues that
the contracting officer’s notice of termination did not become effective until thirty
days after Appellant received the notice on November 4, 2006, thereby entitling
Appellant to payment of breach damages for those thirty days as well. In total, Appellant argues that he should be
compensated for the period beginning
Respondent argues that it did not
breach the contract by refusing access to Appellant’s substitute because Appellant
had neither sought nor received clearance for his substitute to enter the
Ridgeland Post Office pursuant to the requirements set out in the Supplier
Screening Requirements clause. Respondent
further argues that its retroactive termination of the contract was effective
Finally, Respondent argues if the Board decides Appellant
is entitled to any additional compensation resulting from a breach, then any
amount otherwise due for the days on which services were not actually provided should
be reduced by the amount of wages that should have been paid to his substitute in
accordance with a wage determination issued pursuant to the Service Contract
Act, 41 U.S.C. §§351–358, in order to prevent a windfall.
We agree that Respondent’s refusal
to permit Appellant’s substitute to perform was proper. While Appellant’s substitute was denied
access to the Ridgeland Post Office by the COR because she erroneously thought
the contract had been terminated, his being denied access was nonetheless appropriate
because Appellant failed to secure proper clearance for his substitute as
required by the contract. The fact that
the COR may have been aware that Appellant desired to have Mr. Davis as his
substitute does not amount to waiver of the requirement to obtain clearance. See CIMPI Transportation
Corporation, PSBCA No. 1203, 1985 PSBCA LEXIS 80,
With his substitute properly denied
access, Appellant’s unavailability to perform the contract requirements is
unexcused and supports the termination on one day’s notice. That the contracting officer's termination
letter did not cite Appellant's failure to perform as the reason for the termination
is of no consequence. A termination on
one day’s notice can be justified by the circumstances at the time of
termination. Appellant’s continued failure
to perform (Finding 4) is such a circumstance.
See Kelso v. Kirk Brothers Mechanical
Contractors, Inc., 16
F.3d 1173 (Fed. Cir. 1994); Derrick Van Greene, PSBCA
Nos. 5093, 5215, 07-2 BCA ¶33,471; Tom Kime, PSBCA No. 3480, 95-1 BCA
¶27,490; Arthur Napier, PSBCA Nos. 3044, 3140, 94-2 BCA ¶26,695.
The termination of Appellant’s contract, however, is not
retroactive to
This leaves as the remaining issues whether
Appellant is entitled to receive any additional compensation and, if so, how
much. We find that Respondent breached
the contract by preventing Appellant from performing services required under
the contract from
Under the contract, the daily value
of performance is established at $76.12 for the purpose of deducting
compensation from Appellant in the event he failed to perform service (Finding
4). We find the daily value calculation is
also suitable for establishing the value to be applied to the seven days for
which Appellant is entitled to receive compensation. Accordingly, Appellant is entitled to receive
$532.84. Respondent argues that any
compensation for the period after
CONCLUSION
Respondent did not breach the
contract by preventing Appellant’s proposed substitute from performing, and the
contract was properly terminated on one day’s notice effective
William A. Campbell
Administrative Judge
Chairman