February 25, 1998

Appeal of

AFV ENTERPRISES, INC.

Under Lease Agreement

PSBCA Nos. 2691 & 3316

 

APPEARANCE FOR APPELLANT:

James H.K. Bruner, Esq.

 

APPEARANCE FOR RESPONDENT:

Margaret E. Harper, Esq.

 

OPINION OF THE BOARD ON MOTION FOR SUMMARY JUDGMENT, OR TO STRIKE PORTIONS OF THE COMPLAINT

 

Appellant, AFV Enterprises, Inc., has appealed from the default termination of its contract to build and lease to Respondent, United States Postal Service, a post office in Slingerlands, New York, and the denial of its claim for specific performance of the parties' agreement or for monetary damages arising out of the same transaction.  Respondent has filed a motion seeking summary judgment in its favor with regard to certain elements of the Complaint.

FINDINGS OF FACT

For the purpose of deciding the motion for summary judgment, we make the following findings of fact.

1.  By letter dated March 15, 1988, Respondent's contracting officer purported to accept an offer from Appellant to construct and lease to Respondent a building to be built on property owned by Appellant.  The "Agreement to Lease" ("Agreement") between the parties recited that the building would be built on property located at:

"The Easterly most . . . portion of lands . . . located on the South side of Kenwood Avenue by the red light of Kenwood Avenue and New Scotland Road intersection.  The [property] shall include a driveway 28' [feet] in width from Kenwood Avenue. . . ."

 

In the March 15, 1988 letter, the contracting officer stated that acceptance was "contingent upon" Appellant's revision of the site plan to include a curb cut on Kenwood Avenue, delete a curb cut on "Carroll Place," and make the building visible from Kenwood Avenue.  The letter also stated that the acceptance was contingent on final clearance by "SHPO" [State Historic Preservation Officer].  (Appellant's Appeal File Tab (AAF) J, N, T).

2.  The Agreement required that the building be completed within 300 days after acceptance of the offer and specified that the building was to be constructed in accordance with drawings identified as "86-NYR-4067" (AAF J).  January 9, 1989, was 300 days after the date of the March 15, 1988 letter.

3.  Paragraph 5 ("Termination for Default - Damages for Delay - Time Extensions") of the General Provisions to the Agreement provided, in part,

"(a)  If [Appellant] refuses or fails to prosecute the work with such diligence as will insure its completion within the time specified in this contract, or any extension thereof, or fails to complete said work within such time, [Respondent] may, by written notice to [Appellant], terminate his right to proceed with the work. . . .

(b) [Appellant's] right to proceed shall not be so terminated . . . if:

(1)The delay in the completion of the work arises from unforeseeable causes beyond the control and without the fault or negligence of [Appellant], including but not restricted to . . . acts of Government in either its sovereign or contractual capacity, . . . or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of both [Appellant] and such subcontractors or suppliers . . . ."  (AAF J).

 

4.  Under paragraph 15(a) ("Licenses, Permits, Safety, Indemnification") of the General Conditions, Appellant was,

". . . responsible for obtaining any necessary licenses and permits required for privately owned buildings, and for complying with any applicable Federal, State, and municipal laws, codes and regulations, in connection with the performance of the work. . . ."  (AAF J).

 

Paragraph 3(g) of the Agreement required Appellant to obtain any necessary permits within 90 days after acceptance of the Agreement, unless the period was extended by the contracting officer (Respondent's Appeal File Tab (RAF) 1).

5.  The parties to the Agreement held a preconstruction meeting on March 29, 1988.  At that meeting, which was attended by Respondent's Real Estate Specialist, the parties agreed that they would change the location of the building on the site primarily because of difficulties involving vehicle access.  The parties agreed that the revised site arrangement would be sketched by Appellant's architect[1] and sent to Respondent's operations office for approval.  (Respondent's Supplemental Appeal File Tab (RSAF) 2, 3).

6.  The current record does not indicate whether Respondent formally approved the revised site plan.  However, the plan, as revised by Appellant's surveyor, was discussed at a meeting of the surveyor and representatives of Respondent's operations office on August 9, 1988, at which time Respondent's representatives agreed that the plan represented the "best possible usage" of the site.  (RAF 13).  The site plan was first formally presented to the Town of Bethlehem[2] Planning Board by Appellant's surveyor on August 22, 1988 (RAF 14).

7.  During the Fall of 1988, Appellant, its surveyor, and Respondent's personnel continued their efforts to provide information required by the Planning Board and participated in one public hearing concerning the project.  The Planning Board's primary difficulty with approving the site was traffic problems related to the location of driveways, although other aspects of the proposed site arrangement also were concerns.  (RAF 15-18, 20‑24).

8.  As of March 1989, Appellant had not yet obtained the permits necessary to allow it to proceed with the project.  By letter dated March 9, 1989, the contracting officer noted that 300 days had passed as of January 9, 1989, and directed Appellant to "show cause" why it should not be declared in default of its obligation under the Agreement.  (RAF 28).

9.  Appellant replied to the show cause notice in a letter from its attorney dated March 10, 1989.  In that letter, Appellant attributed the delays to three primary causes -- the change in location of the building on the site (as discussed at the preconstruction meeting), delays by Appellant's surveyor in making some submittals to the Planning Board, and the "exhaustiveness" of the Planning Board review process.  In the letter, Appellant alleged that the question of extending the completion date of the contract because of the need to get the revised site arrangement approved by the Planning Board had been discussed by the parties' representatives, and that Respondent's representatives had indicated that any such extension would be discussed after there was an indication that the Planning Board would approve the new location. Appellant also stated that it had accommodated the concerns of the Planning Board in its latest proposal and expected approval of the plan at one of the Planning Board's upcoming meetings -- on April 4, April 18, May 2, and May 16.  (RAF 29).

10.  The site plan was not brought up for approval at any of the above Planning Board meetings.  (Respondent's Motion for Summary Judgment, Exhibit (REx) 5).

11.  By letter dated July 9, 1989, the contracting officer terminated the contract for default for Appellant's failure to complete the work by January 9, 1989.  Appellant filed a timely appeal, which was docketed as PSBCA No. 2691.[3]  (RAF 31, 32).

12.  On April 7, 1992, Appellant filed a claim with the contracting officer seeking specific performance of the Agreement or, in the alternative, damages for improper termination.  The alternative damages sought by Appellant consisted of lost rent for the basic lease term of ten years in the amount of $893,760; lost rent for the twenty years of option periods (four terms of five years each) in the total amount of $2,652,498; and costs incurred by Appellant in connection with the Agreement in the total amount of $23,400.[4]  In a decision dated June 25, 1992, the contracting officer denied Appellant's claim, and the appeal from that denial was docketed as PSBCA No. 3316.  (Notice of Appeal, PSBCA No. 3316; Complaint, filed November 12, 1992).[5]

DECISION

Summary judgment may be granted only if no genuine issues of material fact exist and the moving party is entitled to judgment as a matter of law.  Celotex Corp. v.

Catrett, 477 U.S. 317, 322 (1986); Mingus Constructors, Inc. v. United States, 812 F.2d 1387, 1390 (Fed. Cir. 1987); Rood Trucking Co., Inc., PSBCA Nos. 3121, 3132, 93-2 BCA ¶ 25,564; On Time Postal Services, Inc., PSBCA No. 2528, 90-2 BCA ¶ 22,698.  Doubts concerning factual issues must be resolved in favor of the nonmoving party.   United States v. Diebold, 369 U.S. 654, 655 (1962); Vienna/Vienna, PSBCA Nos. 2505, 2816, 92-3 BCA ¶ 25,042.

Respondent argues that Appellant failed to meet the completion date under the Agreement to Lease and was not entitled to an extension of time.  In particular, Respondent argues that none of the reasons cited by Appellant in its letter of March 10, 1989 (Finding 9), constituted an excusable delay.  Respondent contends that it did not request that the building be moved to a different location on the site, but that the move was the result of a suggestion by Appellant's surveyor.  Further, Respondent contends that the move, even if determined to be its responsibility, should have caused a delay of no longer than two weeks.

In the alternative, Respondent argues that it could have terminated the Agreement for Appellant's failure to pursue the work with such diligence as to ensure that the work would be completed on time.

Appellant makes two principal arguments that it contends should lead to the denial of Respondent's summary judgment motion with respect to the propriety of the default termination.  Appellant argues first that it was delayed because of the requirement that the site plan be revised to make the building visible from Kenwood

Avenue, a requirement it argues was imposed by Respondent and which led directly to the change in building location and Appellant's subsequent inability to obtain the necessary permits from the town.  Appellant also argues that the schedule against which delays are measured is uncertain because the fact that the site plan revision was made a contingency in Respondent's acceptance may have prevented the Agreement from even coming into effect until August 1988, when the site plan was finally revised.

Appellant's second major argument is that even if there was a basis for terminating the Agreement at one time, Respondent lost the right to terminate because it failed to exercise that right promptly.  Appellant argues that it relied on that failure and continued, with Respondent's knowledge, in its efforts to secure Town approval of the project.  Appellant argues further that Respondent, having lost its right to terminate, failed to reestablish a reasonable completion date so as to revive its right to terminate for default.

Having considered the record and arguments of the parties, we conclude that there exist genuine questions of material fact with regard to the circumstances surrounding the change in location of the building on the site and the effects of that change on Appellant's ability and obligation to prosecute the project within the time allowed by the Agreement.  The record indicates that the change in location was discussed at the preconstruction meeting after award of the Agreement and that Appellant agreed to work on moving the building to another location on the site.  The

record does not allow us to determine whether Respondent directed such a change or whether Appellant initiated the change, or to determine what the effect of the change was on Appellant's ability to complete the project within the required schedule, regardless of which party initiated it.  Similarly, there are insufficient facts to address whether Respondent waived any performance schedule by its conduct.  Finally, Respondent's "contingent" acceptance of Appellant's proposal raises the question, which cannot be resolved from the existing record, of when the Agreement actually came into effect so as to begin the running of the 300-day construction period.

Accordingly, Respondent's motion for summary judgment with respect to the propriety of the default termination is denied.

As to Appellant's affirmative claim, Respondent argues that it is entitled to judgment as a matter of law on Appellant's claim for specific performance of the Agreement because such relief is in the nature of injunctive relief, which is beyond the Board's authority to order.

Respondent is correct.  As a matter of law, specific performance is not available to Appellant as a remedy in a Board proceeding.  Mr. and Mrs. Edward R. Ester, PSBCA No. 1559, 87‑2 BCA ¶ 19,719; See also James A. Crosby, PSBCA No. 3673, 95-2 BCA ¶ 27,754.  Accordingly, Respondent's motion is granted with respect to that portion of the appeal.

However, we do not agree that Respondent is entitled to summary judgment on the issue of the recoverability of rent lost during the base and option terms of the

Agreement.  With respect to the base term, Respondent argues only that Appellant would most likely not have generated any profits, given that it was a new business venture whose principals had little or no experience in commercial construction.  However, we agree with Appellant that the mere fact that Appellant was a new venture, with inexperienced principals, does not by itself support a factual finding that Appellant would not have earned a profit on the base term and, therefore, does not lead to the conclusion that Appellant may not recover damages.

The situation is similar with respect to the loss of profits during the option periods.  Respondent correctly points out that the options were exercisable at the sole discretion of the Postal Service.  Based on this, Respondent argues that any loss of profits from the option periods would be particularly speculative and uncertain -- i.e., not within the contemplation of the parties at the time the Agreement was entered into.  The factual determination as to whether such damages were within the contemplation of the parties may turn on evidence of the expectations of the parties when the Agreement was entered into, with respect to the likelihood of the Postal Service exercising its options.  The current record contains no evidence on this point from either side.  While making the necessary factual showing may be more difficult for Appellant with respect to the option periods, Appellant will be given the opportunity to do so.  Accordingly, this portion of Respondent's motion is denied.

Respondent's motion for summary judgment is granted with respect to Appellant's demand for specific performance, but is otherwise denied.

David I. Brochstein

Administrative Judge

Vice Chairman

 

I concur:

James A. Cohen

Administrative Judge

Chairman

 

I concur:

Norman D. Menegat

Administrative Judge

Board Member



[1]  Appellant's surveyor was the person who actually performed the work of revising the site plan.

[2]  The Hamlet of Slingerlands is within the Town of Bethlehem, New York.

[3]  In December 1989, at Appellant's request, this appeal was dismissed without prejudice pursuant to 39 C.F.R. §955.31.  The appeal was restored to the Board's active docket in October 1991.

[4]  Contractor: $1,900; Surveyor: $5,000; Legal Fees: $16,500.

[5]  Neither the claim nor the contracting officer's decision is in the record.