December
23, 1996
Appeal
of
WILLIAM
ROACH
Under
Contract No. HCR 08234
PSBCA
No. 3335
APPEARANCE
FOR APPELLANT:
Richard
M. Flynn, Esq.
APPEARANCE
FOR RESPONDENT:
Deborah
A. Davis, Esq.
OPINION OF THE BOARD
Appellant, William
Roach, has appealed the termination of his mail transportation contract with
Respondent, United States Postal Service.
Respondent terminated the contract for default based on Appellant’s
alleged failure to perform according to the requirements of the contract.
A hearing was held, and
the parties submitted post-hearing briefs.
FINDINGS OF FACT
1. On June 11, 1991, Respondent renewed contract
HCR 08234 with Appellant for transportation of mail between Pleasantville and
Marmora, New Jersey, with stops at a number of post offices along the route,
for the period July 1, 1991, through June 30, 1992. Respondent’s South Jersey Division Logistics
office, in Bellmawr, New Jersey, oversaw the operation of the route, although
the contracting officer was at the Philadelphia Transportation Management
Sectional Center. (Hearing Transcript,
Pages (“Tr.”) 9, 82, 128; Appeal File, Pages (“AF”) 7-70).
2. The contract required Appellant to “carry all
mail tendered for transportation under this contract, whatever may be its size
and weight, with certainty, celerity, and security . . . .” (AF 20, Basic Surface Transportation Services
Contract General Provisions, PS Form 7407T, March 1989, General Provision
4(a)).
3. Appellant was to provide the service using
one 1200 cubic foot vehicle, and the contract required him to have sufficient
stand-by equipment of the same type readily available to permit maintenance and
to prevent delays from emergencies such as mechanical failures (AF 14-15,
Contract Section 15).
4. The contract required Appellant to “comply
with all safety measures for protection of the general public and operating
personnel.” (AF 21, General Provision
5).
5. The termination clause of the contract, Termination by the Postal Service for
Default, provided, in part, “The Contracting Officer may terminate this
contract for default: (1) For Contractor’s failure to perform service according
to the terms of the contract.” (AF 26,
General Provision 16(a)(1)).
6. The contract required Appellant to make five
round trips each weekday and four on Saturday between Pleasantville and
Marmora, New Jersey, making stops at Northfield, Linwood, Somers Point and
Ocean City. Appellant was not required
to stop at each post office on every trip.
When the contract was renewed in 1991, the contract schedule was modified,
but the new schedule proved unworkable.
Over the first weeks of the renewal term, the parties met and worked out
adjustments to the schedule by trial and error, and a new schedule was prepared
to be effective July 27, 1991. (Tr.
94-95, 110, 131, 152-153, 323, 339-341, 448; AF 4-6, 10, 88-93;
Supplemental Appeal File, Tab (“SAF”) 2).
7. The first round trip of the day, Trips 11/12,
leaving Pleasantville at 3:00 a.m., was added at the time of renewal. Pleasantville was the hub office for receipt
of mail from South Jersey Division for further distribution to the post offices
along Appellant’s route and for receipt of their outgoing mail for dispatch to
South Jersey (Tr. 144, 324). The main
reasons for adding Trips 11/12 were to free the cramped and congested dock at
Pleasantville for further mail processing by dispatching the mail received
before 3:00 a.m. from South Jersey to the post offices on Appellant’s route and
to get those offices their mail earlier, especially Ocean City. (Tr. 99-100, 144, 326; SAF 4). Trip 11 went only as far as Ocean City,
scheduled to arrive there at 3:30 a.m.
Appellant was to leave Ocean City at 3:50 a.m. for the return (inbound)
Trip 12, arriving back at Pleasantville at 4:15 a.m. The next outbound trip, Trip 1, was scheduled
to leave Pleasantville at 4:30 a.m. On
Monday through Friday, at the conclusion of Trip 4, an inbound trip, Appellant
was to lay over at Northfield, the stop immediately preceding Pleasantville,
from 8:40 a.m. until 11:45 a.m. and arrive at Pleasantville at noon, just
before the next outbound trip. On
Saturday, Appellant was not scheduled to have a layover at Northfield but was
to conclude Trip 4 at Pleasantville at 8:55 a.m. under the schedule that became
effective July 27, 1991. The original
renewal schedule had required a 9:00 a.m. return to Pleasantville to conclude
Trip 4 on Saturday. (AF 5, 10; see SAF
4).
8. On the trips for July 22 (AF 120), 23 (AF
119) and 24, 1991 (AF 118), Appellant did not return to Pleasantville at
the conclusion of Trip 4 even though the written schedule required such return
(Tr. 275-276, 341; AF 5, 10, 118, 119, 120).
A Contract Route Irregularity
Report, PS Form 5500,[1]
was issued for each instance, and a copy was sent to Appellant (Tr. 83,
86). In the space provided for the
contractor’s response on the copy of each of the 5500s, Appellant noted that he
had acted according to verbal instructions of South Jersey Logistics not to
return to Pleasantville on Trip 4. (Tr. 340-343,
350-352; AF 118-120).
9. On October 26 (AF 116), November 2 (AF 114),
9 (AF 113), and 16 (AF 112), 1991, all Saturdays, Appellant’s driver did
not return to Pleasantville for the last stop of Trip 4 as required by the
schedule (Finding 7). Forms 5500 were
prepared by the Transportation Requirements Analyst (“TRA”) at South Jersey who
discovered the deficiencies during her review of the monthly log of all highway
contract trips to and from Pleasantville.
The 5500s were sent to Appellant in a batch at the end of November. (Tr. 25, 72, 86, 353, 362-364).
10. On October 10 and November 1, 1991, Appellant
failed to perform Trips 11/12 (Tr. 275; AF 5, 115, 117). These failures were reported on PS Forms
5500, which were sent to Appellant (Tr. 86), and a pro rata deduction was
made from Appellant’s pay. (AF 101,
115, 117). On November 1, heavy
rains and flooding had made at least part of Appellant’s route impassable,
although he could have made it to Northfield (Tr. 172, 355-361, 391).
11. On November 21, 1991, at Pleasantville,
Appellant’s driver refused to load two containers of outgoing First Class mail
for the Northfield Post Office, which was the first stop on the route, even
though there was room for the containers on the truck. The driver stated that he had been directed
by Appellant to load no more than the fifteen containers already on the
truck. This information was written up
on a 5500 by the TRA, and sent to Appellant.
(Tr. 86, 365-366, 389, 413; AF 111).
12. In a November 25 letter, signed by the South
Jersey Logistics Manager but drafted by the TRA, Respondent called Appellant to
a meeting to be held December 5, 1991, at South Jersey Division (AF
86-87). The letter included copies of
the 5500s and listed the performance deficiencies. The letter identified the last four occasions
of a failure to return to Pleasantville after Trip 4 (Finding 9), as well as
the missed Trips 11/12 (Finding 10), as “Omitted Service”. (AF 86-87).
At the meeting, Respondent’s officials advised Appellant of their
concerns about his performance under the contract and notified Appellant that
unless he maintained 100% satisfactory performance thereafter, Respondent would
take further action (Tr. 95-98, 384; AF 84-87).
13. At the December 5, 1991 meeting, Appellant
did not complain that he was not receiving 5500s relating to the performance
deficiencies, and he was reminded of the need to reply to any 5500s issued to
him. (Tr. 58, 86, 131, 188, 193).
14. Appellant failed to perform Trips 11/12 on
February 28 (AF 108; contra Tr. 403-404) and April 28, 1992 (AF
107). Forms 5500 were issued and sent to
Appellant, each noting the reason given by Appellant or his driver
contemporaneously why the runs were missed:
“driver alarm was set wrong” (February 28), and “mechanical truck
problems” (April 28) (Tr. 275; AF 107, 108).
A 5500 was also issued noting that Trips 11/12 were omitted on January
22, 1992 (AF 109), and recording Appellant’s contemporaneous explanation,
“could not get truck started”. On
January 24, Appellant responded further on the 5500 that had been sent to him,
stating that the driver had notified Pleasantville of the problem and
suggesting that the truck did arrive, albeit late. (Tr. 402; AF 109).
15. On May 5, 1992, Respondent and Appellant
extended the expiration date of the contract by one year, from June 30, 1992,
to June 30, 1993 (Tr. 65-66, 398, 422-423; AF 3-4).
16. Appellant failed to perform Trips 11/12 on
May 22 and 23, 1992 (Tr. 275, 309; AF 105-106; contra Tr. 406-409). Appellant received 5500s relating to these
dates that contained Respondent’s local official’s characterization of the
deficiency: “Failure to run Trip #11&12 of contract schedule” (May 22) and
“Did not perform Trips 11&12" (May 23). Appellant responded to the former on May 29
and the latter on June 4. In the section
of the 5500 designated for the contractor’s response, Appellant wrote for each
incident that he had been repairing the E-track of the truck (associated with
the restraint system in the interior of the truck box) (Tr. 86-87, 181; AF
105-106). Appellant did not state on the
5500s that he had performed the trips (AF 105-106).
17. On April 16, 1992, deductions were made from
Appellant’s pay for the missed service of February 28, and on June 1, 1992,
deductions were made for the missed service on January 22, April 28 and May 22
(Tr. 15, 192; AF 99, 100). Copies of the
documents effecting the deduction were sent to Appellant (AF 99, 100).
18. In a May 29, 1992 memorandum, drafted by the
TRA for her manager’s signature, the South Jersey Division asked the
contracting officer to take action to correct the service deficiencies on the
route (AF 77-78).
19. In a June 10, 1992 letter, the contracting
officer advised Appellant that the omitted service of January 22, February 28,
April 28, and May 22 (Findings 14, 16) constituted unsatisfactory service. The four instances were plainly identified by
the contracting officer as omitted service.
Appellant was notified that the letter was “a final warning, and that
the Postal Service may terminate [his] contract for failure to perform unless
satisfactory service is restored within ten (10) days of receipt of this
letter, and maintained for the remaining term of the contract.” (AF 75).
Appellant received the letter on June 12 (Tr. 416; AF 76), but he
did not reply or object to the content of the letter or complain of not
receiving 5500s relating to performance deficiencies (Tr. 58, 86-87, 192).
20. Appellant did not perform Trips 11/12 on July
2 and 3, 1992 (Tr. 292-293, 302; SAF 3; contra 424-428). Respondent’s group leader mail handler on the
platform at the Pleasantville Post Office completed 5500s showing that
Appellant had failed to make Trips 11/12 on those days (Tr. 274; SAF 3). The 5500s, or reissued versions of them, were
sent to Appellant (Tr. 86-88, 103, 302; AF 103, 104; SAF 3). The group leader had noted on Form 5500 for
July 3 “Driver called sick, but could not get in contact with sub.
driver.” The 5500 for July 2 contained
no explanation for the failure. (SAF 3).
21. Based on those reports of failure to perform
on July 2 and 3, and a thorough consideration of the entire record of
Appellant’s performance since the 1991 renewal, the contracting officer
terminated Appellant’s contract on July 21, 1992, citing General Provision
16(a)(1), for Appellant’s failure to perform service according to the terms of
the contract. The contracting officer
based her decision primarily on the instances of omitted service. (Tr. 11-19, 73; AF 122-123). This appeal followed.
DECISION
Respondent argues
that the default termination was justified by Appellant’s many failures to
perform according to the requirements of the contract, which failures are
documented in the PS Forms 5500, Contract
Route Irregularity Reports.
According to Respondent, the deficiencies were serious and continuing,
and Appellant was warned through meetings with Respondent’s personnel and the
final warning letter of the contracting officer that further deficiencies would
not be tolerated. According to Respondent,
the subsequent two instances of omitted service, when considered with
Appellant’s performance over the past year, justified the termination for
default.
Appellant argues that
the performance deficiencies reported on the 5500s did not occur or were
excusable. He contends that many of the
5500s were false and were issued by or at the direction of the TRA in South
Jersey, who, because of a disagreement with Appellant, had targeted his
contract for termination. He contends
the termination of his contract was unjustified and resulted from the bad faith
actions of Respondent’s officials.
Furthermore, he argues that the 5500 process was not followed and that,
except on a few occasions, he was not given copies of the 5500s promptly and
afforded an opportunity to respond to the charges in them. Finally, he argues that Respondent has not
shown that any service deficiencies on his part had any adverse impact on
Respondent’s operations and that, therefore, termination was not justified.
Respondent has the
burden of proving that the termination was justified by demonstrating that
Appellant failed to perform in accordance with the contract. Lisbon Contractors, Inc. v. United States,
828 F.2d 759, 765 (Fed. Cir. 1987); Patricia J. Stevens, PSBCA No. 3272,
94-1 BCA ¶ 26,419 recon. denied 94-2 BCA ¶ 26,951. It has met that burden.
Appellant failed to
complete Trip 4 on four successive Saturdays in October and November 1991
(Finding 9) and from October 1991 through the termination in July 1992,
Appellant omitted service on Trips 11/12 at least seven times (Findings 10, 14,
16) and was late or omitted service on those trips one additional time, January
22, 1992 (Finding 14). Additionally,
Appellant’s driver refused to carry all the available mail on November 21, 1991
(Finding 11). Respondent advised Appellant
in the December 1991 meeting of its dissatisfaction with Appellant’s
performance and that it would not tolerate more performance deficiencies
(Findings 12, 13). More instances
of omitted service occurred, and on June 10, 1992, the contracting officer gave
Appellant a written final warning that further unsatisfactory performance could
be cause for termination of the contract (Findings 14, 16, 19). The July 2 and 3 failures to run Trips 11/12
(Finding 20) justifiably caused the contracting officer to review
Appellant’s performance over the entire term of the renewal contract, and the
performance deficiencies over that time were sufficient to justify termination.[2]
We are not persuaded
by Appellant’s testimony that for most of the instances stated by Respondent to
be nonperformance of Trips 11/12, he actually performed the trips, albeit
late. Except regarding the January 22,
1992 trip, there is no evidence that Appellant made such contentions
contemporaneously. While suggesting in
response to the 5500 of January 22, 1992, that he was only late (Finding 14),
Appellant made no similar response regarding February 28 and April 28
either through the 5500 or after he received the June 10 final warning that
listed those instances as omitted service (Findings 14, 19). In responding to the 5500s for May 22 and 23,
1992, Appellant stated that, for both mornings, he was repairing the E-track in
the truck. He did not say at that time that
he was only slightly late but made the trips (Finding 16), which is what he now
contends. Surely Appellant would have
also contemporaneously objected to Respondent’s nonperformance characterization
if he had only been slightly late.
When Appellant
received the contracting officer’s June 10, 1992 final warning letter
noting the instances of omitted service (Finding 19), he knew that Respondent
had issued 5500s for the identified instances and that Respondent considered
that Trips 11/12 on January 22, February 28, April 28 and May 22 were not
performed.[3] Appellant did not respond to the contracting
officer at that time or make any effort to correct what he now contends were
improper characterizations of his slightly late arrivals as omitted
service. Additionally, deductions were
made from Appellant’s pay based on the instances of omitted service (Finding
17), and surely Appellant would have promptly complained had he believed that
such deductions were unjustified. Under
these circumstances, the written contemporaneous reports are entitled to
greater weight than Appellant’s contrary testimony presented at the
hearing. See United States v.
United States Gypsum Co., 333 U.S. 364, 396 (1947).
Respondent has shown
that Appellant did not meet the contract requirements. Therefore, the burden shifts to Appellant to
present evidence of excusable causes, see Patricia J. Stevens,
PSBCA No. 3272, 94-1 BCA ¶ 26,419 at 131,429 recon. denied 94-2 BCA
¶ 26,951; Pamela J. Sutton, PSBCA No. 1622, 88‑3 BCA
¶ 21,031 at 106,237, or to show that the termination was an abuse of the
contracting officer's discretion, see Jesse A. Farmer, PSBCA No.
2702, 91-3 BCA ¶ 24,181 at 120,941; Quality Environment Systems, Inc.,
ASBCA No. 22178, 87-3 BCA ¶ 20,060 at 101,569.
The failures to
return to Pleasantville on Trip 4 on successive Saturdays after the amendment
of the schedule (Finding 6) are not excusable.
We do not accept Appellant’s argument that the requirement to return to
Pleasantville on Saturdays was added to the schedules without his knowledge. Appellant signed the modification of which
the new schedule was a part and must be presumed to know what was in the
schedule. See Marine Design
Technologies, Inc., ASBCA No. 39391, 94-1 BCA ¶ 26,355. Furthermore, both the original and new
schedules required that Appellant return to Pleasantville at the conclusion of
Trip 4 on Saturdays.
Additionally,
Appellant’s driver’s refusal to carry two containers of First Class mail on
November 21, 1991 (Finding 11), is a material breach of Appellant’s duties
under the contract (Finding 2), and Appellant has not shown the refusal to be
excusable. Mail transportation
contractors are held to strict requirements to carry all of the mail tendered,
and it is Appellant’s burden to demonstrate that for safety reasons, his driver
was justified in refusing to take the two containers of mail. See Arnette B. Fleming Hauling,
Inc., PSBCA No. 2872, 91‑2 BCA ¶ 23,868 at 119,567; Estelle
McCormick, PSBCA No. 1030, 83‑2 BCA ¶ 16,574; Road Service, Inc.,
PSBCA No. 1023, 83‑1 BCA ¶ 16,218 at 80,588. Appellant argued that to have placed the two
containers sideways at the back of the truck would have violated the contract’s
safety requirements (Finding 4) and would have endangered the driver when
unloading at stops down the line. The
reason given by the driver at the time, however, was simply that he had been
instructed by Appellant not to load more than 15 containers on the truck even
though 17 would fit, and there is no evidence that 17 containers would have
exceeded the capacity of the truck. Moreover,
the containers left behind were destined for Northfield, the first stop on the
route, so they would not have interfered with the safe performance of the rest
of Appellant’s route. Appellant did not
demonstrate that loading the containers, for which there was room on the truck,
constituted a hazard so significant that refusing to carry mail tendered by
Respondent, in violation of the express contract requirements (Finding 2),
was excusable. See Pamela J.
Sutton, PSBCA No. 1622, 88-3 BCA ¶ 21,031.
The performance
deficiencies considered most significant by the contracting officer were the
instances of omitted service (Finding 21), and failing to make a scheduled trip
is a serious violation of the contract requirements. The 3:00 a.m. trip obviously caused Appellant
problems, because it is the only trip from the entire schedule that Appellant
totally omitted, and he missed it on at least seven[4]
occasions. Under the circumstances of
this appeal, mechanical problems with his vehicle or the driver oversleeping or
his own illness do not constitute excuses for failure to perform Trips
11/12. Appellant was responsible for
assuring that the contract was performed, even at 3:00 a.m., and was to have
available back-up equipment and substitute drivers to use in the event his
vehicle was unavailable or his driver could not perform (Finding 3). See B.C. Topps d/b/a B.C. Topps
Transport, PSBCA No. 2241, 89‑1 BCA ¶ 21,563. The pattern of omitted service on this
contract demonstrates a failure to provide for satisfactory, reliable
service. Additionally, refusing to carry
mail tendered is a serious violation of the requirements of Appellant’s
contract. Therefore, the failures to
complete Trip 4, the omissions of Trips 11/12 and the refusal to carry mail
provided the contracting officer reasonable grounds for terminating the
contract. See Ernest Johnson,
PSBCA No. 3658, 95-2 BCA ¶ 27,692; William Cimpi, PSBCA No. 2695,
91-1 BCA ¶ 23,390; Henry Lee Yon, PSBCA No. 932, 81-1 BCA
¶ 15,076.
Appellant’s argument
that any missed trips had no impact on Respondent’s operation and thus are not
grounds for termination is rejected.
Pleasantville’s was a crowded and congested dock, and getting the mail
for the downstream post offices off the dock was a prime reason for setting up the
3:00 a.m. trip in the first place (Finding 7). That Appellant might have carried the same
mail and equipment on the day’s second trip, leaving Pleasantville at
4:30 a.m., does not mean that the failure to perform Trips 11/12 was
excusable or nonchargeable. Appellant
contracted to perform Trips 11/12, and his failure to do so is a contract
violation, notwithstanding his belief that later delivery adequately served the
post offices’ needs. See J
& M Trucking, PSBCA No. 2804, 92-1 BCA ¶ 24,598 at 122,724.
Appellant did not
show that the system of issuing 5500s was flawed. Appellant contends that the termination
should be set aside because Respondent’s officials failed to follow
Respondent’s established procedure for reporting performance deficiencies. First, he argues that there was no informal
discussion with him regarding correction of any performance failures as he
contends is required by Respondent’s procedures as set forth in the USPS Mail Transportation Procurement
Handbook (Finding 8, Footnote 1).
However, Respondent’s officials worked with Appellant to resolve
schedule problems at the beginning of the renewal term, met with Appellant to
discuss his performance on the route, and wrote to him addressing his
performance (Findings 6, 12, 19). Furthermore,
Appellant has not suggested how his failures to perform Trips 11/12 because of
mechanical or driver failures would have been corrected by additional informal
discussions. Thus, Appellant has not
shown that Respondent failed to communicate with him regarding his performance
of the route and has not demonstrated that he was prejudiced by Respondent’s
handling of the correspondence, discussions and meetings relating to his
performance.
Next, Appellant
argues that the 5500s were unreliable because they were issued by persons who
did not observe first hand the deficiencies reported. Of the 5500s found to support the termination
for default, those relating to the failure to return after Trip 4 (Finding 9)
were prepared by the TRA from monthly logs, and she did not personally observe
the deficiencies. Likewise, the 5500
relating to Appellant’s driver’s refusal to carry mail on November 21, 1991
(Finding 11), was prepared by the TRA, evidently based on information reported
to her because she was not present when the incident occurred. However, Appellant has not disputed that the
instances reported on those 5500s occurred as reported, so whether the forms’
preparer actually observed the events is academic. The other 5500s that support our findings
were prepared by employees of Respondent who appear to have had first hand
knowledge of the irregularities reported.
With respect to the critical 5500s for July 2 and 3, 1992 (Finding 20),
Appellant vigorously disputed their accuracy, contending that he performed
Trips 11/12 on both days and that the group leader whose name appears on them
was not at work those days and prepared the 5500s later. Based on our observation of the witnesses and
evaluation of the testimony and documents regarding the events of July 2 and 3,
we have found that the group leader’s reports of omitted service on those dates
were accurate.
Finally, Appellant
has argued that Respondent did not send copies of the 5500s to him. Those for the failures to complete Trip 4
were not sent until the end of the month following their occurrence (Finding
9), but the evidence is that the others were sent to him promptly (Findings 10,
11, 14, 16, 19). His contemporaneous
responses on many of the 5500s demonstrate he did receive them, and he did not
complain to Respondent’s officials of nonreceipt when he indisputably became
aware that 5500s were being issued (Findings 13, 19). We do not find that Appellant was prejudiced
by a failure to receive 5500s.
Appellant has not
shown that Respondent failed to follow the procedures for issuance of 5500s in
any material way. He has not shown that
he was prejudiced by the process followed or that Respondent’s handling of the
5500s would be a basis for overturning the termination for default that is
otherwise justified. See B&E
Mail Transport, Inc., PSBCA No. 947, 82‑2 BCA ¶ 15,912 at 78,870; H.
L. Clemons, PSBCA No. 569, 1980 WL 3063, February 29, 1980.
Finally, Appellant
has not shown bad faith on the part of Respondent’s officials. Appellant has argued strenuously that the
Transportation Requirements Analyst at South Jersey had targeted his contract
for termination because of differences between them. He produced evidence that several months
after his contract was terminated, the TRA had taken actions adverse to another
highway contractor who had fired a driver who was a friend of hers. Two other contractors testified that the TRA
could be vindictive. Appellant also
demonstrated that the TRA drafted correspondence for her manager’s review,
revision and signature (Findings 12, 18).
This does not amount to a showing that she administered Appellant’s
contract in bad faith. There was no
credible evidence that she fabricated 5500s relating to Appellant’s performance
or that she told any other postal official to do so, as Appellant suggested, or
that any of her actions were motivated by a desire to harm Appellant. Appellant has not met his burden of
demonstrating that the TRA acted in bad faith.
See Kalvar Corp. v. United States, 211 Ct. Cl. 192,
198-199, 543 F.2d 1298, 1301-02 (1976) cert. denied, 434 U.S. 830
(1977); Patricia J. Stevens, PSBCA No. 3272, 94-1 BCA ¶ 26,419 at
131,430 recon. denied 94-2 BCA ¶ 26,951.
Furthermore, the
contracting officer acted independently in terminating the contact, and only
did so after a thorough review of the contract files (Finding 21). The evidence does not show that the TRA had
any influence over the contracting officer, or that the contracting officer had
any knowledge of hard feelings that might have existed between Appellant and
the TRA. There is no evidence of ulterior
motives or bad faith by the contracting officer in making the termination
decision, see Jaehee Yoshimoto, PSBCA Nos. 2315, 2749, 92-1 BCA
¶ 24,504 at 122,314; J & M Trucking, PSBCA No. 2804, 92-1
BCA ¶ 24,598 at 122,723, and the contracting officer did not act arbitrarily or
abuse her discretion.
The appeal is denied.
Norman
D. Menegat
Administrative
Judge
Board
Member
I
concur:
James
A. Cohen
Administrative
Judge
Chairman
I
concur:
David
I. Brochstein
Administrative
Judge
Vice
Chairman
[1] PS Form 5500, Contract Route Irregularity Report, is a
form used by Respondent to notify transportation contractors of deficiencies in
their performance. Respondent's
employees at the point where the irregularity occurs note the deficiency on the
form, and a copy of the form is to be sent to the contractor through the
contract's administrative official (South Jersey in this case). The form provides space for the contractor to
reply and provide any explanation for the identified irregularity. (Tr. 14-15, 29-34). If irregularities persist or become more
serious, Respondent’s guidelines require the administrative official to follow
the following sequence if each preceding step does not achieve satisfactory
service: informal discussions with the
contractor to try to correct the deficiencies, a conference, a certified letter
requesting improvement and, finally, referral to the contracting officer for
action. (Handbook PO-513, February 1990,
USPS Mail Transportation Procurement
Handbook, 2.6.2). The Mail
Transportation Procurement Handbook is intended only for the internal guidance
of Respondent’s officials in the performance of their duties. (Transmittal Letter 2, February 1990, USPS Mail Transportation Procurement
Handbook).
[2] We have not
considered the July 1991 failures of Appellant to return to Pleasantville after
Trip 4 (Finding 8) as breaches of the contract requirements. The original renewal schedule had proved
unworkable, and the parties were in the process of revising it (Finding
2). Oral permission had been given
Appellant to vary the contract schedule in certain respects, and the parties
were refining the schedule as they went along.
Respondent has not demonstrated that those failures constituted breaches
of a contract schedule the parties had agreed to.
[3] Although the
contracting officer did not list the omitted service of May 23 in her final
warning letter, Appellant had already received the 5500 for that date which
clearly stated that Appellant had not performed Trips 11/12 (Finding 16).
[4] Appellant contended
that he performed Trips 11/12 on January 22, 1992, and he did provide a
contemporaneous response to the 5500 for that date suggesting that he arrived
at the post office late. The portion of
the 5500 in the appeal file showing the time Appellant said he arrived is
illegible, so it is not possible to determine whether he was late for Trips
11/12 or missed 11/12 but arrived in time for the next trip, Trip 1, leaving at
4:30 a.m. (Finding 14). Whether omitted or late, however, Appellant
failed on that date to perform according to the requirements of the contract
because his truck could not be started, and there is no evidence that Appellant
had a backup vehicle available as required by the contract (Finding 3). Additionally, we have not counted the
November 1, 1991 omitted service, considering nonperformance of that trip to be
excused because of bad weather and flooding along the route (Finding 10).