September 15, 1995

Appeals of

ALTA CONSTRUCTION COMPANY

Under Contract No. 239952-85-V-0073

PSBCA Nos. 1463 & 2920

 

APPEARANCE FOR APPELLANT:

Thomas M. Rhule, Jr.

 

APPEARANCE FOR RESPONDENT:

D. D. Anna, Esq.

 

OPINION OF THE BOARD

 

Appellant, Alta Construction Company, seeks to recover legal fees incurred following the termination for default of its term construction contract, which termination was later converted by the Contracting Officer to a termination for convenience of the Postal Service.

Background

These appeals have been the subject of four previous Opinions:  Alta Construction Company, PSBCA No. 1463, 90-1 BCA ¶ 22,527 and 90‑3 BCA ¶ 22,966; and PSBCA Nos. 1463 & 2920, 92-2 BCA ¶ 24,824 (recon. denied 92-3 BCA ¶ 25,128) and 94-3 BCA ¶ 27,053.

The background of these appeals was set out in some detail in the latest of our Opinions, Alta Construction Company, 94-3 BCA ¶ 27,053, and will not be repeated here.  The parties opted against a hearing and elected to have the remaining issue in these appeals considered on the record.  Appellant submitted supplemental evidence and both parties submitted briefs.

FINDINGS OF FACT

1.  The "Termination for Convenience of the Postal Service," clause of Appellant's contract provided that as to work performed, the contractor was to be paid the cost of such work, the cost of settling claims arising out of the termination of subcontracts, and a reasonable profit.  Under the clause, allowability of such costs was to be governed by the principles set out in Section 15 of the Postal Contracting Manual (PCM).  The clause also provided that the amount of such payments could not exceed the "total contract price...."  Excepted from this maximum payment limitation was:

"The reasonable cost of the preservation and protection of property incurred pursuant to [paragraph (b)(9); and any other reasonable cost incidental to][1] termination of work under this contract, including expense incidental to the determination of the amount due to the Contractor as the result of the termination [of]1 work under this contract."  (Respondent's Appeal File Tab (RAF) 1, PS Form 7391, "GENERAL PROVISIONS FOR FIXED-PRICE CONSTRUCTION CONTRACTS" (July 1984)).

 

2.  PCM section 15-205.42, "Termination Costs," provided, in part,

"Contract terminations generally give rise to the incurrence of costs, or the need for special treatment of costs, which would not have arisen had the contract not been terminated.  Cost principles covering these items are set forth below.  They are to be used in conjunction with the remainder of this part in termination situations.

***

 

"Settlement Expenses.  Settlement expenses, including the following are generally allowable:

(1) Accounting, legal, clerical, and similar costs reasonably necessary for:

(I) The preparation and presentation to contracting officers of settlement claims and supporting data with respect to the terminated portion of the contract..., and

(ii)  The termination and settlement of subcontracts...."  (RAF 38).

 

3.  PCM section 15-205.31, dealing with "Professional and Consultant Service Costs," provides, in part:

"Cost of legal ... services ..., incurred in connection with ... the prosecution of claims against the Postal Service, are unallowable ...."  (Id.).

 

4.  The Contracting Officer terminated Appellant's contract for default on August 20, 1985.  Appellant filed its first notice of appeal on November 14, 1985.  In June 1990, the Contracting Officer issued a letter converting the default termination to one for the convenience of the government.  (RAF 14, 17).

5.  The legal services at issue here were rendered between September 12 and October 14, 1985, as follows:

"9/12/85  Telephone conference w/Tom Rhule re. procurement; meeting w/co-counsel re. same  1.85

 

9/18/85  Meeting w/Tom Rhule, Jr. re. overview and letter to bond company 3.25

 

9/23/85  Conference w/ client  .6

 

9/23/85  Preparation of letter to bonding company re. procurement against bond       2.0

 

9/24/85  Telephone conference w/Dennis Wills re. procurement; telephone conference w/Robert Coven; meeting w/T. Rhule  3.25

 

9/25/85  Conference w/co-counsel  1.0

 

9/26/85  Conferences w/ co-counsel re response to letter  1.6

 

10/1/85  Telephone conferences w/client re. status of situation w/bonding company  .75

 

10/11/85  Telephone conferences w/Erie Insurance re. Alta Construction bond  .55

 

10/14/85  Meeting w/client re. necessity of suit.. 3.0 

 

17.85

 

 

 

Professional Services:

 

17.85 hours at $85 per hour  $1,517.25"

 

(RAF 30(Statement of charges prepared by Appellant's attorney))

 

6.  Appellant believed it had been unfairly treated under a prior term construction contract.  Under that contract, Appellant believed that the Postal Service managers had assigned it, as second low bidder, only difficult construction jobs at remote locations -- jobs which were difficult or impossible for it to perform at a profit.  Appellant believed, further, that the Postal Service managers had been specifically biased in favor of the other term construction contractor in the assignment of projects.  As a result, Appellant had unsuccessfully attempted to avoid the award of a contract to it in this instance when it became aware that it was again the second low bidder.  Following the default termination of this contract, Appellant sought legal advice in its dealings with both its bonding company and with the Postal Service office administering the contract.  Appellant was apparently under the impression that Respondent could and would continue to attempt to assign the bonding company only the most costly and difficult assignments under the terminated contract, to Appellant's detriment[2] and, therefore, Mr. Rhule discussed with the attorney strategies Appellant might use if this occurred.  At Mr. Rhule's October 14 meeting with the attorney, the conversation centered on accomplishing these strategies while avoiding litigation against either the Postal Service or the bonding company.  Appellant's attorney was also specifically asked to try to help persuade the Contracting Officer to convert the default termination to one for convenience.  ((Appellant's Appeal File, Tab 31) Affidavit of Thomas M. Rhule, Jr., pages 18‑19).

DECISION

As we stated in our previous Opinion, Alta Construction Company, 94-3 BCA ¶ 27,053 at 134,816, in order to recover, Appellant must show that the legal fees at issue here qualify for exclusion from the maximum payment limitation set out in the Termination for Convenience clause -- i.e., that the legal fees are recoverable above the contract price, which otherwise would be the ceiling for recoveries under the convenience termination.  Specifically, Appellant must show that the fees were "reasonable cost[s] incidental to termination of work under this contract, including expense[s] incidental to the determination of the amount due to the Contractor as the result of the termination of work under this contract."  Further, Appellant must show that the claimed fees were not incurred in connection with the prosecution of claims against the Postal Service.

Appellant's primary argument is that it resorted to hiring an attorney after the termination because it feared that Respondent, having asked the bonding company to take over the contract, would continue to assign the bonding company the most costly and burdensome projects.  Appellant wanted the attorney to help develop a strategy to prevent that from happening and to deal with the bonding company on Appellant's behalf.  Appellant argues that it also asked the attorney to help persuade the Contracting Officer that the contract had been improperly terminated for default and that the termination should be converted to one for convenience.

Respondent cites a number of statements, which it refers to as admissions, in one of Appellant's earlier submittals and argues that these statements and the remainder of the record demonstrate that Appellant is not claiming the kinds of attorney fees allowable under the termination for convenience clause.  The exact basis for Respondent's arguments is not stated and is not otherwise made clear in its brief.

Having considered the record, we conclude that Appellant may recover a portion of the legal fees it has claimed.[3]  The remaining legal fees were not incurred in connection with the prosecution of a claim against the Postal Service.  In this case, Appellant's attorney was not engaged to conduct litigation.  Further, the largest percentage of the attorney's time apparently was spent in dealing with Appellant's bonding company.  Although he was also asked to help persuade the Contracting Officer to convert the default termination to one for convenience, there is no indication those efforts involved any resort to or preparation for litigation.  While not dispositive of the issue, we note that the notice of appeal was not filed until a month after the attorney ceased rendering the services for which the claim was made.  Further, Thomas Rhule, Jr., a principal in Appellant, has represented Appellant in all its litigation -- both in its protests before award and in the appeals before this Board.  Therefore, we conclude that the fees identified in the record as related to dealings with the bonding company or the Contracting Officer do not represent costs of prosecuting a claim against Respondent, and Appellant is not, on that basis, barred from recovering these fees.  See e.g., Acme Process Equipment Co. v. United States, 347 F.2d. 538, 545 (Ct. Cl. 1965); E.W. Eldridge, Inc., ENGBCA No. 4879, 93-1 BCA ¶ 25,355 at 126,293; Paul E. McCollum, Sr., ASBCA No. 23269, 81-2 BCA ¶ 15,311; A.C.E.S., Inc., ASBCA No. 21417, 79-1 BCA ¶ 13,809; Baifield Industries, Division of A-T-O, Inc., ASBCA No. 20006, 76-2 BCA ¶ 12,096, aff'd on recon. 76-2 BCA ¶ 12,203.

We are then left with the question of whether the remaining legal fees constituted "any ... reasonable cost[s] incidental to the termination of work under this contract, including expense incidental to the determination of the amount due to the Contractor as the result of the termination of work under this contract."  If so, Appellant may recover the fees over and above the maximum payment limitation set out in the termination for convenience clause.

We conclude that the fees represent "reasonable costs incidental to the termination of work" under the contract.  These costs were incurred as a direct result of the default termination.  Given that Appellant believed that its surety would be required by Respondent to assume the burden of performing only unprofitable work under the contract,[4] it was not unreasonable for Appellant to have sought legal help in connection with the termination, particularly in its dealings with the surety.  Since, as we have found, the legal fees incurred in dealing with the surety and the Contracting Officer were not incurred in the prosecution of a claim against the Postal Service, Appellant may recover those fees above the maximum payment limitation that would otherwise apply.

The appeal is sustained in part.  Appellant may recover the fees incurred, other than those excluded in note 3, above, plus Contract Disputes Act interest.

David I. Brochstein

Administrative Judge

Board Member

 

I concur:

James A. Cohen

Administrative Judge

Chairman



[1]  The termination for convenience clause will be read to include the bracketed language (although that language does not appear in the July 1984 version of PS Form 7391 incorporated into the contract), since that language was included at §18‑541.7 of the Postal Contracting Manual, which contained the termination for convenience clause that was required to be used at the time this contract was awarded.  See PCM Transmittal Letters 33-35; PCM Circulars 84-4 through 85-4.  See also Enclosure A to RE&B Bulletin No. DC-84-1, dated January 6, 1984 (which provides for use of the October 1979 version of PS Form 7391 in term construction contracts); G.L. Christian & Associates v. United States, 160 Ct. Cl. 1, 312 F.2d 418, reh. den. 320 F.2d 345, cert. den. 375 U.S. 954 (1963).  In our earlier Opinion, at 94-3 BCA ¶ 27,053, we reached the same conclusion for the purposes of deciding the motion for summary judgment.  As neither party has objected to this determination, we adopt it in connection with this Opinion.

[2]  The Postal Service had asked the bonding company to take over the contract and perform work at Fayetteville, West Virginia (RAF 33).  Appellant apparently believed that Respondent could and would continue to assign the bonding company unprofitable jobs during the remaining term of the terminated contract -- for which Appellant might ultimately be financially responsible.

[3]  Notwithstanding the Board's repeated reminders to Appellant that recovery would hinge on providing a description of the services actually rendered, information concerning the nature of the legal services is found only in the brief billing statement prepared by Appellant's attorney (Finding 5) and, to a very limited extent, in Appellant's affidavit (Finding 6).  Appellant has failed to offer any evidence describing the services rendered on September 12, 23, 25, and 26.  Therefore, costs incurred for those services are not recoverable.

     [4]  And, presumably would hold Appellant financially liable for any losses.