March
29, 1993
Appeal
of
HOTEL
SYSTEMS, INC.
Under
Contract Nos. 489990-87-V-A001, 482271-86-V-A007, 489990-87-V-A008,
482271-84-V-A018, 482271-86-V-A095, 482271-85-V-A020
PSBCA
Nos. 3253-3258
APPEARANCE
FOR APPELLANT:
G.
Michael Gruber, Esq.
APPEARANCE
FOR RESPONDENT:
Judith
L. Schlossberg, Esq.
OPINION OF THE
BOARD ON MOTION FOR SUMMARY JUDGMENT
Hotel
Systems, Inc., Appellant, has appealed the denial of its claims for the cost to
repair a number of vehicles Appellant leased to the Postal Service, Respondent,
which Appellant contends were damaged while in Respondent's custody. The contracting officer denied all of the
claims as untimely, not addressing the merits, and these appeals followed. Respondent has filed a motion for summary
judgment, contending it is entitled to judgment as a matter of law because the
claims were untimely filed. The
following findings of fact are made for purposes of this motion.
FINDINGS
OF FACT
1. The Postal Service's Dallas Procurement
Service Office awarded Appellant the 6 contracts at issue in these appeals
during the period 1984 through 1986 (Appeal File for PSBCA No. 3253 ("AF
3253") Tab 8; AF 3254 Tab 8; AF 3255 Tab 8; AF 3256 Tab 6; AF 3257 Tab 8;
AF 3258 Tab 8).
2. Each of the contracts included the
"General Provisions for Vehicle Hire Contracts," PS Form 7476, July
1980, General Provision GP-6 of which provides, in part:
"LIABILITY
PROVISIONS.
(a) Contractor's
Vehicles. The Postal Service
shall be responsible for loss of, or damage to, the Contractor's vehicles while
in its custody only when caused by the act or negligence of any officer or
employee of the Postal Service acting in the scope of his employment, provided
that such officer or employee is not the Contractor, an employee of the
Contractor, or a dependent of the Contractor.
In no event shall the Postal Service be responsible for ordinary wear
and tear. The Contractor shall file a
claim with the Contracting Officer within sixty days after the earliest of the
following dates:
(1) the date
that the vehicle is returned to the custody of the Contractor or agent for
servicing, repair, or as a result of termination or expiration of the contract,
(2) the date
of receipt by the Contractor or his agent of written notice from the
Contracting Officer advising of damage to the vehicle, or
(3) the date
of receipt by the Contract [sic] or his agent of notification that the vehicle
is no longer required by reason of termination or cancellation." (Id.)
3. General Provision GP-8 (c) of each of the
contracts permitted either party to cancel the contract after the second year
of performance by giving notice to the other 120 days in advance of the
effective date of the cancellation (id.).
4. Respondent exercised its right of
cancellation under 5 of the contracts, establishing effective dates for the
cancellations in 1989 (AF 3253 Tab 7; AF 3254 Tab 7; AF 3255 Tab 7; AF 3257 Tab
7; AF 3258 Tab 7). The term of the sixth
contract, number 482271-84-V-A018 (PSBCA No. 3256), expired May 1, 1990 (AF
3256 Tab 6, Tab 3, Declaration of Saundra J. Smith, submitted by Respondent,
which appears in Tab 3 of each of the appeal files ("Smith
Declaration"), ¶ 6).
5. The vehicles were jointly inspected and
returned to Appellant on March 3, 1989, and April 1, 1989, for the 5 cancelled
contracts and on May 15, 1990, for the sixth contract. Damage to the vehicles noted during the
inspection was recorded on the PS Form 4577, "Hired/Borrowed Vehicle
Condition Report," prepared for each vehicle (AF 3253 Tab 4; AF 3254 Tab
4; AF 3255 Tab 4; AF 3256 Tab 4; AF 3257 Tab 4; AF 3258 Tab 4).
6. On or about November 11, 1991, Appellant
submitted to Respondent claims under each of the contracts for the cost of
repairing damage to a number of the vehicles (id.). The date of receipt by the contracting
officer is not apparent from the record, but for purposes of this motion we
find the claims were filed no earlier than November 11, 1991.
7. In separate decisions issued during February
and March of 1992, the contracting officer denied the claims under each of the
contracts because they were filed beyond the time allowed in the contract (AF
3253 Tab 3; AF 3254 Tab 3; AF 3255 Tab 3; AF 3256 Tab 3; AF 3257 Tab 3; AF 3258
Tab 3). The contracting officer did not
reach the merits of the claims, stating in each decision:
"The receipt of the
subject claims are considerably outside the time restriction imposed by the
contract nor was any reason offered for the late filing. If the Postal Service had been put on notice
that the filing of the claims would be delayed this could have been taken into
consideration. However, since this was
not the case the provision of the contract must be adhered to. Therefore, the subject claims . . . are
denied." (Id.)
Prejudice to the Postal Service Resulting From
Late-Filed Claims
8. When a lessor's
vehicle is damaged while in the custody of the Postal Service, it is the usual
practice of the Dallas Procurement Service Office and the postal organizations
directly administering the vehicle hire contracts under the control of the
Dallas Procurement Service Office to furnish written notice to the contractor
and to send a copy of the notice to the contracting officer (Smith Declaration
¶12). When accumulated damage claims are
received from the contractor at the end of the lease, these notices are
reviewed by Respondent to determine if the damage had been the subject of a
notice, and if so, whether the notice reflected damage resulting from a cause
that would relieve the Postal Service from liability, such as third party responsibility
or vandalism (Smith Declaration ¶13).
9. A review of the
Postal Service's files after receipt of Appellant's claims revealed that the
files no longer contained copies of all documents that were sent to the
contractor during the lease periods (Smith Declaration ¶14). The record does not identify particular
documents or types of documents that are missing or state that this condition
exists for all of the contract files relevant to these appeals.
10. Many of the
postal drivers and others with knowledge of how the vehicles might have been
damaged are no longer working at the stations where the vehicles were used
(Smith Declaration ¶16). Documents
relating to who was driving a particular vehicle when it might have been
damaged were not retained (id.).
The record does not state when these records were discarded.
Payment of Similar Late Claims
11. Appellant held
two other vehicle hire contracts, 482271‑85‑V‑A024 and
482271-85-V-A002, with the Dallas Procurement Service Office (Appellant's September
28, 1992 Supplemental Appeal File).
12. Vehicles
covered by these leases were returned to Appellant on July 18, 1989, and
November 10, 1989. Damage noted during
inspections of the vehicles when they were returned to Appellant was recorded
on the PS Form 4577 for each vehicle (id.).
13. In September
1991, Appellant filed accumulated damage claims for a number of the vehicles
leased under the A002 and A024 contracts (id.).
14. The
contracting officer on contract 482271-85-V-A002 disregarded the recommendation
of his representative that the claims be denied as untimely, considered the
claims on their merits, and on October 28, 1991, approved for payment the
amounts requested by Appellant (id.).
By final decisions dated December 18, 1991, the contracting officer for
contract 482271-85-V-A024 decided the claims under that contract on their
merits, allowing part of each claim and denying part (id.).
DECISION
Respondent contends it is entitled to judgment as a
matter of law because Appellant filed its claims approximately 2½ years (1½
years for contract 482271-84-V-A018 (PSBCA No. 3256)) after return of the
vehicles, well beyond the 60-day period allowed in the contracts (Finding 2)
for filing such claims. Appellant argues
that there are material issues of fact in dispute and that Respondent is not
entitled to judgment as a matter of law.
A motion for summary judgment may be granted only if no
genuine issues of material fact exist. Celotex
Corp. v. Catrett, 477 U.S. 317, 322 (1986); Mingus Constructors, Inc. v.
United States, 812 F.2d 1387, 1390 (Fed. Cir. 1987); Rood Trucking Co.,
Inc., PSBCA Nos. 3121, 3132, __ BCA ____ (November 6, 1992); On Time
Postal Services, Inc., PSBCA No. 2528, 90-2 BCA ¶ 22,698. For purposes of the motion, doubts concerning
factual issues must be resolved in favor of the nonmoving party. United States v. Diebold, 369 U.S.
654, 655 (1962); Vienna/Vienna, PSBCA Nos. 2505, 2816, 92-3 BCA
¶ 25,042. It is not the role of the
Board in considering a motion for summary judgment to resolve the genuine
issues of material fact, but to determine if such issues are present. See Anderson v. Liberty Lobby, Inc.,
477 U.S. 242, 249 (1986); American Federal Contractors, PSBCA No. 1424,
86-2 BCA ¶ 18,891 at 95,306; D & S Universal Mining Co.,
Inc. v. United States, 4 Cl.Ct. 94, 96 (1983).
In Jake Sweeney
Auto Leasing, Inc., PSBCA Nos. 2859-2862, 92-1 BCA ¶ 24,444, and Jake Sweeney Auto Leasing, Inc., PSBCA
No. 2918, 91-3 BCA ¶ 24,161, the Board concluded that absent prejudice to
the Postal Service, the contracting officer must consider on their merits
vehicle hire contractors' claims for damage to leased vehicles even though the
claims were filed beyond the 60 days allowed in the contract liability
provision. In both cases, we found no evidence
that the Postal Service was prejudiced by the failure of timely notice. See also Gene Gibler, PSBCA No.
1278, 1985 WL 8933, February 26, 1985.
In its motion, Respondent argues that it has demonstrated
that prejudice to the Postal Service resulted from Appellant's long delay in
filing its vehicle damage claims, and that there is no genuine issue of
material fact on this point. It urges
that the two Jake Sweeney Auto Leasing, Inc. cases cited above are,
therefore, distinguishable, and that the Board should find for Respondent as a
matter of law (Memorandum in Support of Respondent's Motion for Summary
Judgment). Although the cited Jake
Sweeney Auto Leasing, Inc. cases hold that a contracting officer must
address the merits of a late-filed vehicle damage claim where there is no
evidence of prejudice to the Postal Service resulting from the delay in filing,
those holdings do not necessarily lead to the conclusion that such claims will
be barred as a matter of law if Respondent demonstrates some measure of
prejudice. When a contracting officer
considers whether to address the merits of a claim filed beyond a claims-filing
limit stated in the contract, "prejudice to [the government] would be
relevant and material in the exercise of such judgment . . . " and
"the exercise of such judgment must be reasonable, not arbitrary or
capricious." Eggers &
Higgins v. United States, 185 Ct. Cl. 765, 785, 403 F.2d 225, 236 (1968); accord
Gulf & Western Indus. v. United States, 6 Cl.Ct. 742, 755
(1984). The extent and significance of
prejudice to the Government resulting from a contractor's delay in filing its
claims are issues of fact, and it is the government's burden to establish that
there are no genuine issues of material fact in this regard. See H.H.O. Co. v. United States,
12 Cl.Ct. 147, 164 (1987); Gulf & Western Indus. v. United States, 6
Cl.Ct. at 755. There is no presumption of prejudice. Id.
Respondent has failed to establish that there are no
material facts in dispute regarding the existence and significance of
prejudice. The general allegations of
lost documents, faded memories and unavailability of witnesses are not
sufficient to demonstrate that Respondent is hampered in defending every damage
claim on each of the contracts. It
demonstrates at most that some documents which may be needed to defend some
parts of the appeals may not be available and some witnesses needed might be
difficult or impossible to find.
Nonspecific allegations of prejudice are not sufficient to meet the
movant's burden of showing that there are no material facts in issue regarding
prejudice to the Postal Service in defending each of the claims asserted by
Appellant, especially where there is evidence that similar claims on other
contracts, also filed well beyond the 60-day period, were considered on their
merits (Findings 11-14). Cf. Radiation
Systems, Inc., ASBCA No. 41065, 91-2 BCA ¶ 23,971 at 119,984. Genuine issues of material fact remain
regarding the specific prejudice that might affect Respondent's defense of each
damage claim.
The motion is denied.
Norman D. Menegat
Administrative Judge
Board Member
I concur:
James A. Cohen
Administrative Judge
Chairman
I concur:
James D. Finn, Jr.
Administrative Judge
Vice Chairman