February 5, 1993

Appeal of

DOBEE INC.

Under Lease Agreement

PSBCA No. 3238

 

APPEARANCE FOR APPELLANT:

John H. Baker, Esq.

 

APPEARANCE FOR RESPONDENT:

Robert E. O'Connell, Esq.

 

OPINION OF THE BOARD ON PARTIAL MOTION TO DISMISS

 

            Appellant, Dobee Inc., has filed an appeal from a Contracting Officer's decision which denied its claim for an equitable adjustment in contract price for repaving work performed under an Agreement to Lease.  Respondent, United States Postal Service, has filed a partial motion to dismiss alleging that the Board has no jurisdiction over portions of Appellant's appeal, as no final decision by the Contracting Officer has been issued on those claims.  Appellant opposes Respondent's motion.  For purposes of deciding the motion, we make the following findings of fact.

                                                                Findings of Fact

            1.  On March 9, 1990, Appellant and Respondent entered into an Agreement to Lease under which Appellant agreed to construct and lease to Respondent a facility in Mulino, Oregon, to be utilized as a post office.  The facility was to be completed within 180 days and a separate lease agreement was to be executed the first day of the month following acceptance by Respondent (Appeal File (AF)-5).  The anticipated effective date of the lease therefore was October 1, 1990.

            2.  The project completion was delayed for certain reasons not relevant to this appeal (AF-18).  On November 13, 1991, a representative of Respondent wrote Appellant and advised that tests would be conducted on the facility's asphalt paving to determine contract compliance (AF-24).  On January 14, 1992, Respondent by letter advised Appellant that the asphalt paving and base aggregate did not comply with contract specifications.  Appellant was directed to take remedial action by removing the existing paving, compact the base aggregate and repave (AF-28).

            3.  On February 6, 1992, Appellant wrote the Contracting Officer and advised that the remedial work had been completed.  However, Appellant disputed the need to perform the work, alleging that the paving as initially performed had been in conformance with the contract requirements.  Therefore, Appellant requested reimbursement of the sum of $28,752 for the asphalt removal and repaving work.  Appellant also requested that the lease for the facility be executed with an effective date of January 1, 1992 (AF-31).

            4.  By letter dated February 25, 1992, the Contracting Officer denied Appellant's request for reimbursement for the pavement removal and replacement work.  The letter also stated that the lease for the facility would be executed March 1, 1992, provided that certain minor corrective action was taken pertaining to the repaving (AF-33).  The lease thereafter was executed with an effective date of March 1, 1992 (AF-34).

            5.  By letter to the Contracting Officer dated April 10, 1992, Respondent again sought reimbursement for the asphalt removal and repaving work (AF-35).  By final decision dated April 30, 1992, the Contracting Officer denied Appellant's claim for reimbursement for the asphalt removal and repaving costs (AF‑38).  This appeal followed (AF-39).

            6.  Appellant thereafter filed its Complaint with the Board.  Paragraph VIII(d) of the Complaint sought a sum of $30,258 for paving removal, recompacting, and repaving.  Paragraph VIII(c) of the Complaint sought $3,699 for construction interest, $357 for real property taxes, and $70 for property insurance, all for the months of January and February 1992.

Decision

            Respondent argues in support of its motion that the Board has no jurisdiction to hear that portion of Appellant's claim relating to damages for construction interest, real property taxes, and property insurance, as Appellant never presented a claim to the Contracting Officer for those items.  Thus, Respondent contends no Contracting Officer's decision on those items of claim was ever issued and the Board is required under the Contract Disputes Act, 41 U.S.C. § 601 et. seq., to dismiss those portions of the appeal.  Respondent relies upon Paragon Energy Corp. v. United States, 227 Ct. Cl. 176, 645 F.2d 966 (1988); RGI Inc., ASBCA No. 38772, 92-2 BCA ¶ 24,839; and Janie Marie Winkle, PSBCA No. 1548, 86-3 BCA ¶ 19,255, to support its position.

            In opposing the motion, Appellant argues that the claim for recovery of construction interest, real property taxes, and property insurance is a claim for damages directly resulting from Respondent's failure to accept the project on January 1, 1992, when Appellant contends it was completed.  According to Appellant, had the Contracting Officer not incorrectly ordered Appellant to do the repaving work the lease for the facility would have been executed effective January 1, 1992, and Appellant would not have incurred the costs in issue.  Thus, reasons Appellant, the interest, tax, and insurance items are components of its overall claim for the repaving work.

            Respondent's position is not well taken.  Paragraph VIII(c) of the Complaint is neither a new claim not presented to the Contracting Officer nor a major revision to the claim presented to the Contracting Officer.  The paragraph seeks an element of damages flowing from the February 6, 1992, claim which requested reimbursement for paving removal and repaving costs and sought a lease commencement date of January 1, 1992.  The claim was subsequently denied by Contracting Officer's final decision of April 30, 1992.[1]  We therefore hold we have jurisdiction to consider whether Appellant is entitled to the relief sought in Paragraph VIII(c) in deciding the appeal.  See Transco Contracting Company, ASBCA No. 28620, 85-2 BCA ¶ 17,977, and cases cited therein.  See also Spradlin Corporation, ASBCA No. 23974, 81-2 BCA ¶ 15,423.

            Accordingly, Respondent's Partial Motion to Dismiss is denied.

James D. Finn, Jr.

Administrative Judge

Vice Chairman

 

I concur:

James A. Cohen

Administrative Judge

Chairman

 

I concur:

David I. Brochstein

Administrative Judge

Board Member



[1] By denying the request for cost reimbursement, the Contracting Officer implicitly denied the request for the January 1, 1992, lease commencement, since granting the cost reimbursement request would have acknowledged the right to an earlier lease commencement date, and Appellant would not have incurred the interest, tax, and insurance costs now requested.