Appeal
of
MELVIN R.
KESSLER
Under Contract No. HCR
25871
PSBCA Nos. 2820,
2972
APPEARANCE FOR
APPELLANT:
Melvin R.
Kessler
APPEARANCE FOR
RESPONDENT:
Deborah A. Davis,
Esq.
OPINION OF THE BOARD
These appeals are from Contracting Officer decisions denying Appellant’s
claims of $62,000 for an alleged breach of contract resulting from the improper
termination for convenience of his contract, and $5,254.88 for attorney fees,
lost wages and unsafe working conditions prior to termination. Only issues relating to entitlement are
before the Board for decision.
FINDINGS OF
FACT
1. On
2. Incorporated into the
contract was PS Form 7407, Basic Surface Transportation Services Contract
General Provisions, Oct. 1986, (GP) which included a Claims and Disputes
Clause. Clause 17, Termination for
Convenience, allowed the Postal Service to terminate the contract, or the right
to perform under it, in whole or in part “when it is in the best interest of the
Postal Service” (AF 10). The Clause
further provided that when so terminated the contractor would be allowed as
liquidated damages an indemnity as provided in Clause 12
(id.).
3. Under Clause 4, Service
Requirements and Prohibitions, the contractor was required to carry all mail
tendered for transportation under the contract “with certainty, celerity, and
security, in accordance with the operating schedule and between points fixed in
the solicitation, as modified from time to time pursuant to Clause 12” (AF
10).
4. The contract contained
Amendment No. 1, effective
“12 Changes in
Service
(a) Service
Changes
(1)
Insignificant Minor Service Changes. -
The Contracting Officer may, at any time, without consulting the
Contractor, issue orders directing an extension, curtailment, change in line of
travel, revisions [sic] of route, or increase or decrease in frequency of
service or number of trips and fixing an adjustment in the contractor’s
compensation which increases the Contractor’s rate of pay by no more than 10% or
$1,000, whichever is less. If the
Contractor believes the increased cost of providing the service required by the
order exceeds the increase made in compensation, he may request an adjustment of
compensation for the service change.
(2)
Other service
changes.
Service changes other than insignificant minor
service changes may be made if the terms of the change, including increases or
decreases in compensation, are agreed to by the Contracting Officer and the
Contractor. Such changes shall be
executed on Form 7406, Amendment to transportation
Contract.”
5.
Appellant was required under the schedule specified in the contract to
deliver mail daily between 9:00 A.M. and 4:15 P.M. along a route that covered
approximately 49.7 miles and involved approximately 150 boxes with stops at the
Ghent, Odd, Josephine, and Princewick Post Offices, all in West Virginia (AF
10).
6. In
February 1990 the Administrative Postmaster at
7. Commencing in 1984 the
Princewick Postmaster dealt with Appellant’s presence in the Princewick Post
Office and occasional personal confrontations, which were usually followed by
apologies by Appellant (Tr 142-43, 144-46). Beginning in early 1989 Appellant’s more
frequently exhibited inappropriate conduct towards the Postmaster, and the
Postmaster for the first time made complaints to her supervisor concerning
Appellant’s conduct (Tr 144-46).
During 1989 and the early part of 1990 Appellant, while on his route,
would remain in the Princewick Office for periods of approximately two hours
daily, sometimes returning for additional stays (Tr 137, 143-44, 155). While at the Princewick Post Office
Appellant harassed and made unwanted advances toward the Princewick Postmaster
(Tr. 137, 142-43, 146, 152-53). The
Princewick Postmaster was disturbed and felt threatened by the violent nature of
Appellant’s conduct (id.; Tr 163).
8. A February 1990 survey
performed on Appellant’s route demonstrated that the mail could be delivered in
two hours less than the time specified in the contract (AF 29; Tr
27).
9. Recommendations to
eliminate time from Appellant’s schedule by making a service change were
forwarded to the Contracting Officer (Tr 19-21). Based on the recommendations made by his
staff along with reports and communications from the field (including letters
from Appellant), the Contracting Officer became convinced that the route should
be restructured to eliminate the excess time from the contract schedule. This, he believed, would lessen or
eliminate the problems at the Princewick Post Office, and would also improve
service to the customers, while at the same time reducing the cost to the Postal
Service. (Tr 25, 27-28, 31, 51-52,
64-66). Cost savings resulting from
the restructuring, however, was a secondary consideration and Respondent was
prepared to relinquish its request for a cost reduction had Appellant agreed to
the time reduction (Tr 49-50, 92, 216; App. Exh. 2).
10. Respondent sent to
Appellant a planned service change dated
11. Appellant in a letter to the Contracting
Officer dated
12. Respondent, after
considering Appellant’s offer, rejected it, stating to Appellant in a letter
dated April 3, 1990, that a reduction of one hour, 45 minutes per day was
justified along with a reduction in compensation of $2,243 per annum (AF 14, 15,
19).
13. Appellant in a letter to
the Contracting Officer dated
14. After further
correspondence, on
15. Faced with the options
of having the problems, which were disruptive of Postal Service operations,
continue until expiration of Appellant’s contract in mid-1992, or terminating
the contract for convenience, the Contracting Officer decided on
termination. The Contracting
Officer’s reasons for terminating the contract for convenience were essentially
the same as his reasons for deciding that the route had to be restructured
(see Finding 8), coupled with Appellant’s refusal to consent to
Respondent’s proposed reduction in the hours. (Tr. 25, 27-28, 29, 31-32, 41-43, 49-50,
51-52, 88-90, 207, 209-10).
16. The Contracting Officer
notified Appellant by a notice dated
17. In a letter dated
18. Appellant’s claim of
$5,254.88 was denied in its entirety by the Contracting Officer in a final
decision dated
19. An attempt by Appellant
to amend his claim by increasing the amount an additional $62,000 for breach of
contract damages was rejected by the Board for failure of certification. Melvin R. Kessler, PSBCA No.
2820, 91-1 BCA ¶ 23,511; on recon., 91-2 BCA ¶ 23,698. Appellant thereafter filed a properly
certified claim dated
20. In a final decision
dated
21. Subsequent to the
termination of Appellant’s contract, a successor contractor performed the same
service on the same route with a two hour and 25 minute reduction in the daily
schedule (Tr 102, 178).
DECISION
In this appeal Appellant contends that in terminating his contract for
convenience the Contracting Officer and his staff exercised bad faith which
constituted a material breach of contract entitling Appellant to damages. Appellant also argues that he was denied
due process by the Contracting Officer who terminated the contract based on
reports from Postal Service employees without first affording Appellant the
opportunity for a hearing.
Respondent argues that the Contracting Officer acted within his
discretion and in the best interest of the Postal Service in terminating the
contract for convenience. Further,
Respondent argues that Appellant has failed to establish the type of evidence
that would support his allegation that the Contracting Officer acted in bad
faith in terminating the contract.
Respondent also contends there are no bases in the record for Appellant’s
claims for attorney fees, lost wages, and unsafe working
conditions.
Both parties agree that, because of the language of Amendment 1 of Clause
12(a) of the contract specifying the requirements and procedures for minor and
other service changes (see Finding 4), the Contracting Officer was
precluded from unilaterally issuing a change in Appellant’s schedule of the
magnitude that would reduce the daily time by one hour and 45 minutes. The interpretation that such change
would be more than an “insignificant minor change” appears reasonable and the
Board will accept it.
Cf. Irving
Stumer, PSBCA No. 1256 (Slip Opn.
Reasons for the termination action were stated fully and forthrightly by
the Contracting Officer. Problems
resulting from Appellant’s conduct towards the Princewick Postmaster were
disruptive to Postal Service operations.
Because the existing schedule in Appellant’s contract allowed for long
lay-over periods at the Princewick Post Office, the Contracting Officer
reasonably concluded that elimination of that excessive time was required. He concluded that reduction of excess
time in the contract would not only tend to ameliorate the difficulties between
Appellant and the Princewick Postmaster, but would improve service to Postal
Service patrons on the route, who would receive their mail earlier in the
day.
As set forth in the contract the Termination for Convenience clause
authorizes the Contracting Officer to terminate the contract when the
termination is in the best interest of the Postal Service. That phrase encompasses a broad reach of
variable and unspecified situations that would allow the Postal Service to
terminate the contract. Under such
a clause Respondent has the right to terminate in its best interest and “in the
absence of bad faith or a clear abuse of discretion the contracting Officer’s
election to terminate is conclusive.”
John Reiner & Co. v. United States, 325 F.2d 438, 442 (Ct. Cl.
1963), cert. denied 377 U.S. 931 (1964); accord Salsbury
Industries v.
Appellant’s allegations of bad faith on the part of the Contracting
Officer in terminating the contract find no support in the record. As indicated in the findings, the
Contracting Officer, confronted with a difficult situation at the Princewick
Post Office, sought, in good faith, to resolve the problem. The evidence is consistent with the
presumption “that public officials act ‘conscientiously in the discharge of
their duties.’” Kalvar Corp. v.
United States, 543 F.2d 1298, 1301-02 (Ct. Cl. 1976), cert.
denied 434 U.S. 830 (1977) (quoting Librach v.
Appellant’s contention that it was improper for the Contracting Officer
and his staff to issue the termination without first affording him a hearing is
without merit. A contracting
officer is under no obligation to hold a hearing before issuing a
termination. Appellant has been
afforded all his contractual and statutory protections against arbitrary action
by the Contracting Officer through the procedure available on appeal to this
Board. Shorthaul Trucking
Co., PSBCA No. 1046 (Slip Opn.
Having found no procedural deficiencies, bad faith, or abuse of
discretion, we conclude that the termination for convenience was properly
issued. That being the case,
Appellant’s recovery is limited to the liquidated damages set forth in the
contract. Paul A. Mason,
PSBCA No. 1187, 84-3 BCA ¶ 17, 572, recon. denied, 85-1 BCA ¶
17,735. Accordingly, the appeal
from the denial of Appellant’s breach of contract claim (PSBCA No. 2972) is
denied.
There is similarly no basis for Appellant’s claim for lost wages,
expenses for unsafe working conditions, or attorney fees in PSBCA No. 2820. Those costs were claimed by Appellant in
connection with Respondent’s proposal to reduce the travel time for Appellant’s
route (see Findings 10, 11).
During a period of approximately 17 days in March 1990, Appellant (and
his substitute driver) followed the shortened schedule. There is no evidence that would support
Appellant’s claim of unsafe conditions.
Rather, the record reflects that the contract could be safely and more
efficiently operated with schedule reductions that were in excess of that
utilized during the March 1990 period.
There is no contract provision or other principle of law that would
authorize paying Appellant for lost wages when he attended a meeting with
Respondent’s representatives, or for the claimed attorney
fees.
Accordingly, Appellant’s appeals are denied.
James E. Lemert
Administrative Judge
Board Member
I
concur:
James A. Cohen
Administrative Judge
Chairman
I
concur:
James D. Finn, Jr.
Administrative Judge
Vice
Chairman