April 21, 1989
Appeal of
MICHAEL N. BECKLOFF
Under Contract No. HCR 44041
PSBCA No. 2249
APPEARANCE FOR APPELLANT:
Michael N. Beckloff
APPEARANCE FOR RESPONDENT:
William R. Gilligan, Jr., Esq.
OPINION OF THE BOARD
This appeal concerns the propriety of a contracting officer's decision terminating for default Appellant's highway transportation contract and assessing damages for trips Appellant did not perform. The parties elected to have the appeal decided on the record without an oral hearing.
FINDINGS OF FACT
1. Michael N. Beckloff (Appellant) and the
United States Postal Service (Respondent) entered into highway transportation
contract HCR 44041 on
2. The contract incorporated the "Basic Surface Transportation Services Contract General Provisions" (PS Form 7407, Oct. 1981), with amendments. Those General Provisions included a standard "Claims and Disputes" clause (clause 2). As pertinent here, clause 16, "Termination by the Postal Service for Default," authorized the Contracting Officer to terminate the contractor's right to continue performance under the contract if the contractor failed to perform service according to the contract terms. However, if the default was found to be excusable, the contractor would be entitled to liquidated damages, as prescribed in clause 12, for a termination for convenience under clause 17 (id.).
3. Clause 13 provided that the contractor was "accountable and answerable in damages for the faithful performance" of the contract obligations; specifically, subparagraphs (b) and (c) provided:
"(b) Subject to subparagraph (c) of this Clause, where the Contractor fails to perform a trip, there shall be forfeited from the compensation due him, and the Contracting Officer may deduct from compensation so due, as damages, the compensation due for the trip, but, where the failure is occasioned by the fault of the Contractor, there may be do deducted a sum not to exceed four times the compensation due for the trip.
(c) The amount of damages may be increased in the discretion of the Contracting Officer, according to the nature or frequency of the failure and the importance of the mail." (id.).
4. Under the contract's Payment provision the contractor was to be compensated at the contract rate in installments at the close of each four-week accounting period subject to any adjustment made under the contract (id.).
5. In July 1987, a Creditor's Bill was filed in
the
6. On September 14, 1987, Respondent received a "Judgment Entry" from the Elyria Municipal Court ordering it to pay all funds and money due Appellant to and through the Clerk of the Court for distribution to the plaintiff until $3,247 was paid in full. A copy of the "Judgment Entry" was sent to Appellant (AF-S).
7. On or about October 14, 1987, the Contracting Officer, the Manager of the Transportation Management Service Center (TMS) at Columbus, Ohio, issued a Contract Route Service Order, a copy of which was sent to Appellant, directing that $3,247 be deducted from Appellant's contract and sent to the Elyria Municipal Court (AF-R). The amount due Appellant for Accounting Period 1-88 (October 1987) of $1,170.57 thereafter was sent to the court (AF-L).
8. Upon learning of Respondent's compliance with the garnishment action Appellant made telephone calls to the TMSC and to the Postal Data Center (PDC) in St. Louis, Missouri (which issued his payment checks), asserting that the garnishment was invalid and that his payment check should be released only to him (Beckloff Affidavit ¶¶ 5/11).
9. On
10.
On
11. Appellant previously had written a letter to the TMSC, dated October 28, 1987, and received November 2, 1987, requesting release of the funds and advising that he would have to cease operations under his contract if there was further delay (AF-P) Beckloff Affidavit ¶ 12).
12. By letters dated November 10 and 11, 1987, to the PDC and to the Cleveland Ohio Logistics Office located in the General Mail Facility, Appellant advised that the Court had set aside the garnishment order and enclosed copies of the Court action. The letters were received November 19 and 16, 1987, respectively. He demanded immediate release of the funds and warned he had no money to enable him to continue operations. He also made telephone calls to the PDC and TMSC to the same effect during that time period (AF-M, N; Beckloff Affidavit ¶¶ 13, 14).
13.
On
14.
On or about
15.
On
16. On
17. On
DECISION
Respondent contends
that Appellant's telephone notice on
Appellant contends that
his repudiation and abandonment of the contract was either excusable or caused
by Respondent's material breach of the contract. Appellant makes three arguments in support of
his position. First, Appellant contends
the garnishment judgment was entered only because an unauthorized Postal
Service employee, "G. F. King," signed for the certified mail which
contained the service of process for the original lawsuit. Second, Appellant contends that he informed
Postal Service officials of the invalid service and they ignored such
information Finally, Appellant argues
that the Postal Service was dilatory in rescinding its garnishment payment
procedures subsequent to its receipt of the
The facts of the
controversy do not support Appellant's contentions, We find the default action was warranted.
The certified letter
containing the service of process for the lawsuit was not sent "restricted
delivery" by the Court. Thus, it
was not improper for the letter to be delivered to an individual at the address
shown on the envelope or for the individual, in this case "G. F.
King." to sign the mail receipt. It
does not appear from the record that there exists any information pertaining to
the letter or its whereabouts after its receipt. Additionally, Appellant has not attempted to
pursue the matter through any means of discovery. We thus find no impropriety by Respondent in
the events pertaining to the matter of the service of process.
Appellant's contention
that Postal Service officials were negligent in ignoring his oral
representations as to improper service of process upon him is without
merit. Once Respondent received notice
of the garnishment proceedings in which it was named a defendant it became a
party to those proceedings. Thus, it was
under the jurisdiction of the
Appellant's final
argument that the Postal Service breached the contract by not acting promptly
to rescind the garnishment payment procedure is likewise not persuasive. The TMSC received the
After receiving the
Regional Counsel's response the TMSC acted with dispatch, issuing a service
order on
We
are unable to find Appellant's actions reasonable, however. This conclusion is supported by a comparison
of the time periods with Appellant's actions.
Appellant received a copy of Respondent's
Therefore,
no legal basis or excuse existed for the action taken by Appellant on
The
record is insufficient to support the assessment of the $1,818 amount against
Appellant, however. The Contracting
Officer calculated the assessment based upon 18 trips Appellant did not
perform, plus a penalty factor, during the nine-working day period November 25
-
In summation, Appellant's appeal as to the propriety of the default termination is denied. The matter is remanded to the Contracting Officer for calculation of the proper amount of reprocurement costs, if any, due Respondent.
James D. Finn, Jr.
Administrative Judge
Vice Chairman
I concur
James A. Cohen
Administrative Judge
Chairman
I concur
Joan B. Thompson
Administrative Judge
Board Member
D I S S E N T
I would find the default termination improper and, therefore, dissent from the majority's decision.
The
determinative issue concerning the default termination is whether Appellant was
justified on
The
panel majority concludes Respondent's actions were reasonable and did not
constitute a material breach. I agree
there was no material breach by Respondent in honoring the court order
garnishing Appellant's contract earnings as Respondent is subject to state
garnishment orders. Beneficial
Finance Co. of New York, Inc. v.
However,
the circumstances changed once Respondent received the court order voiding the
garnishment and releasing Respondent from any obligations. I disagree that its actions thereafter were
reasonable in the circumstances of this case although the time sequences by
themselves in ordinary circumstances may not be unreasonably long. Respondent had an implied duty to cooperate
with Appellant. Its failure to do so or
to act diligently could constitute a material breach of contract. See Malone v.
Respondent emphasizes that Appellant was on notice of the garnishment but failed to take court action before his earnings were sent to the court. Appellant was a small, owner-operated contractor and receipt of pay for his past-performed service was vital. This was known to Respondent's personnel who were charged with supervising the administration of the contract. That Appellant failed to understand that Respondent would honor the garnishment even though he told Respondent's personnel the garnishment was invalid (a position upheld by the court), and did not take court action until his earnings were sent to the court, does not excuse Respondent's delay after receiving the order rescinding the garnishment.
This
is not a case where Appellant slept on his rights once the court rescinded the
garnishment. In a letter received by the
TMSC on
Knowing
then that Appellant was legally entitled to receive his contract earnings and
that they were vital to his small business, Respondent should have taken
special measures to assure that Appellant would receive the next check due
him. However, other than the TMSC
telefaxing the copy of the court order to the Regional Counsel, no special
measures were taken. Appellant's
November 20 check was sent to the court - some 18 days after Respondent received
the court's order rescinding the garnishment.
As late as
In
view of my conclusion that Appellant was relieved from any consequences arising
from the default termination because Respondent materially breached the
contract, I believe any assessment of damages would be inappropriate. This would not preclude future consideration
of Appellant's short notice on
Therefore, I would sustain Appellant's appeal as to the default termination and the assessment of damages, but would dismiss Appellant's request for damages other than those provided by the contract for a convenience termination.
Joan B. Thompson
Administrative Judge
Board Member